"I realise that some of my criticisms may be mistaken; but to refuse to criticize judgements for fear of being mistaken is to abandon criticism altogether... If any of my criticisms are found to be correct, the cause is served; and if any are found to be incorrect the very process of finding out my mistakes must lead to the discovery of the right reasons, or better reasons than I have been able to give, and the cause is served just as well."

-Mr. HM Seervai, Preface to the 1st ed., Constitutional Law of India.

Saturday, October 20, 2018

Opportunity of Hearing to Arbitrators? Arbitration & Conciliation (Amendment) Bill 2018

We had done several posts (see here, here, here, and here) critiquing various aspects of the Arbitration & Conciliation(Amendment) Bill, 2018 (2018 Bill) that is to be taken up by the Rajya Sabha in the coming winter session.In this relatively short post, we discuss a proposed amendment that requires reconsideration.

Section 6(b) of the 2018 Bill proposes two provisos to Section 29A(4) of the Arbitration and Conciliation Act, 1996 (1996 Act), one of which is the focus of this post. This proviso grants an opportunity of hearing to the arbitrator/ arbitral tribunal in the reduction of fee. It reads: “Provided also that the arbitrator shall be given an opportunity of being heard before the fees is reduced.”

To provide a brief background, the 1996 Act was amended in 2015 wherein Section 29A was introduced. Section 29A(1) fixed a period of twelve months from the date the tribunal enters upon reference to pass the arbitral award. Section 29A(3) provides for extension of up to six months based on agreement between the parties. Section 29A(4) provides that in case the award is not made within twelve months or the extended period, the court can order the termination of the arbitrator’s mandate.

Proviso to Section 29A(4) states that in extending the period, if the court finds that the tribunal was responsible for the delay, the court could reduce the fee of the tribunal. It is in respect of this proviso that the further provisos are sought to be added.  The 2018 Bill in adding a proviso seeks to grant the arbitrator/ tribunal an opportunity of hearing while considering whether to reduce the fee or not. 

This provision has been made pursuant to the recommendations of the Hon’ble Mr. Justice (Retd.) Srikrishna Committee. The relevant portion of the Report reads:

The Committee is also of the view that the power of the court in the provisos to section 29(4) and (6) to substitute the arbitrator(s) or order a reduction in the fees of the arbitrators when hearing an application for extension under section 29(5) is rather peculiar. These provisions ought to be modified, as the arbitrator is not being heard before he / she is penalised, as only the parties to the arbitration are before the court. Even if such an opportunity were to be afforded, practically, it would lead to problems affecting the integrity of the arbitral process. Arbitrators would be wary of being foisted with a reduction in fees and have a perverse incentive to rush through proceedings to render the award within the stipulated time period. Further, if an application for reduction of fees of the arbitral tribunal were to be denied and an extension granted, it would strain relations between the tribunal and the party applying for the same. The punitive nature of these provisions may also act as a deterrent for reputed arbitrators from accepting domestic arbitrations...  There also exist no provisions empowering the court to order a reduction of the fees of the arbitrator… A new sub-section should be inserted in section 29A providing that where the court seeks to reduce the fees of the arbitrator(s), sufficient opportunity should be given to such arbitrator(s) to be heard.”

The recommendation seeks to protect the interest of the arbitrator/ tribunal when it comes to reduction of fee. 

It is submitted that if this amendment is implemented, it would only lower the position of the arbitrator/ arbitral tribunal to the level of a party to the arbitral proceedings. Section 36 of the 1996 Act treats an award almost equivalent to the decree of a civil court. Although the arbitrator is a creation of the contract, the jurisdiction exercised is nearly the same as that of a District Court or of the original side of a Chartered High Court. The arbitrator/ tribunal is not even a necessary or a proper party in the proceedings relating to setting aside awards: it is sufficient if the record of the tribunal is handed over to the court. Given all these aspects, it is not correct to lower the position of the arbitral tribunal to that of a party in the proceedings. Therefore, it is not in the right spirit of the law to make the arbitrator a party to the proceedings. For the same reasons, it is not correct for the court to reduce the fee of the arbitrator. Would the court reduce the salary of judges if the proceedings drag on due to repeated adjournments?

If proceedings are pending before courts under Section 29A, parties would rarely seek reduction by withholding certain documents evidencing delay on their part since the other side would be likely to use such suppression of documents against the first party in the court or in the arbitral proceedings. If the arbitrator considers such reduction to be unreasonable, she could very well stop acting as the arbitrator. Hence, by the very nature of the proceedings, the arbitrator's interests are duly protected.  

In view of the above, the following can be done:
  • The proviso to Section 29A(4) can be deleted.
  • Instead, the Council to be established under Part IA of the 1996 Act could frame rules to the effect that grading of arbitrators should be on the basis of whether the arbitrators are able to strictly comply with the time limits provided in Section 29A.
  • If the amendments are passed without considering these aspects, courts should construe this proviso to provide an opportunity of hearing to arbitrators only in exceptional cases. 

More on the 2018 Amendments in another post.

Trade, Law and Development: Call for Submissions

Call for Submissions from Trade, Law and Development

Call for Submissions
Special Issue onTrade Facilitation
Founded in 2009, the philosophy of Trade, Law and Development has been to generate and sustain a constructive and democratic debate on emergent issues in international economic law and to serve as a forum for the discussion and distribution of ideas. In keeping with these ideals, the Board of Editors is pleased to announce Trade Facilitationas the theme for its next Special Issue (Vol. XI, No. 1).
Trade facilitation is the simplification, modernisation, and harmonisation of international trade procedures. It helps simplify customs procedures by reducing costs and improving their speed and efficiency through a multilateral understanding. The Trade Facilitation Agreement (‘TFA’) entered into force on February 22, 2017 and is one of the first major new agreements reached by the member countries of the WTO since its establishment in 1995. It contains provisions for expediting the movement, release and clearance of goods,sets out measures for effective cooperation between customs and other appropriate authorities on trade facilitation, and contains provisions for technical assistance and capacity building in this area.
There is extensive empirical data to suggest that trade facilitation can significantly boost trade. However, several concerns exist regarding the projected benefits of the TFA, its implementation, and its enforcement in an increasingly protectionist trade environment. There is also uncertainty as to how the TFA will bring uniformity and consistency in the border management of developing and least-developed countries and the role of the Committee on Trade Facilitation in this respect. Moreover, most regional and bilateral preferential trade agreements negotiated in the recent past have incorporated varying provisions related to trade facilitation. It is unclear whether the TFA has been successfully able to achieve broad application of these commitments. These subjects have not received sufficient attention from mainstream academia yet. Consequently, existing literature is inadequate to effectively equip policymakers to deal withsuch issues.
Alongside this, India has been championing trade facilitation in services at the WTO.Trade in services too faces various barriers at and behind the border, which poses difficulties for service providers from developing countries like India in accessing key markets. India’s proposal focussed on making existing market access meaningful through reduction in transaction costs arising from unnecessary regulation. The proposal received a mixed response. Some Members like China even supported the proposed agreement going beyond the scope of domestic regulation under GATS, while others expressed concerns regarding the need for a separate legal text for trade facilitation in services and the nature and scope of the obligations put forth therein.
This Special Issue, currently scheduled for publication in July 2019, will provide an ideal platform to deliberate on trade facilitation initiatives at the WTO and how they relate to more regional initiatives.Accordingly, the Board of Editors is pleased to inviteoriginal and unpublished submissions for the Special Issue on Trade Facilitation forpublication as ‘Articles’, ‘Notes’, ‘Comments’ and ‘Book Reviews’.
Manuscripts may be submitted via e-mail, ExpressO, or through the TL&D website. For furtherinformation about the journal and submission guidelines, please visit www.tradelawdevelopment.com.
In case of any queries, please feel free to contact us at: editors[at]tradelawdevelopment[dot]com.

LAST DATE FOR SUBMISSIONS: 15thFebruary, 2019



PATRON: P.P. Saxena ADVISORS: Raj Bhala|JagdishBhagwati | B.S. Chimni | Glenn Wiser |Daniel B. Magraw, Jr. | Vaughan Lowe | Ricardo Ramirez Hernandez | W. Michael Reisman | M. Sornarajah FACULTY-IN-CHARGE: Rosmy Joan BOARD OFEDITORS: Mridul Godha | RakshitaGoyal | AnirudhGotety | Noyonika Nair | Radhika Parthasarathy | Ipsiata Gupta | Shreya Singh | AveralSibal |Gautami Govindarajan |Iti Mishra | MihirMathur| RishabhMeena | Shefalika Shekhawat | Amogh Pareek | Anirudh Sood | Apoorva Singh | Parnika Mittal | SahilVerma | SarthakSingla

Saturday, October 6, 2018

Union of India v Hardy Exploration & Production (2018: SCI): A Critique

We had a guest post in this blog providing a descriptive comment on the decision of the two judge Bench in Union of India v Hardy Exploration & Production (India) Inc (2018: SCI)("Hardy I") referring the matter to a larger Bench of the Supreme Court. Thereafter, a three judge Bench of the Supreme Court consisting of Dipak Misra, CJI, AM Khanwailkar & Dr DY Chandrachud, JJ. have decided the issue ("Hardy II") on 25.09.2018 (see here for the decision). This post discusses the decision.

Agreement Concerned:

The agreement between Union of India ("UOI") and Hardy Exploration & Production (India) Inc ("HEPI") provided, among other things:

"32.1 This contract shall be governed and interpreted in accordance with the laws of India.
32.2 Nothing in this contract shall entitle the contractor to exercise the rights, privileges and powers conferred upon it by this contract in a manner which will contravene the laws of India.
33.2 Matters which, by the terms of this Contract, the Parties have agreed to refer to a sole expert and any other matters which the Parties may agree to so refer shall be submitted to an independent and impartial person of international standing with relevant qualifications and experience appointed by agreement between the Parties. Any sole expert appointed shall be acting as an expert and not as an arbitrator and the decision of the sole expert on matters referred to him shall be final and binding on the Parties and not subject to arbitration.
If the Parties fail to agree on the sole expert, then the sole expert shall be appointed, upon request by one of the Parties, by the Secretary General of the Permanent Court of Arbitration at the Hague, from amongst persons who are not nationals of the countries of any of the countries of any of the Parties.
33.3 Subject to the provisions herein, the Parties hereby agree that any unresolved dispute, difference or claim which cannot be settled amicably within a reasonable time may, except for those referred to in Article 33.2 be submitted to an arbitral tribunal for final decision as hereinafter provided.
33.5 Any Party(ies) may, after appointing an arbitrator request the other Party(ies) in writing to appoint the second arbitrator. If such other Party(ies) fails to appoint an arbitrator within forty five (45) days of receipt of the written request to do so, such arbitrator may, at the request of the first Party(ies), be appointed by the Secretary General of Permanent Court of Arbitration at Hague, within forty five (45) days of receipt of such request, from amongst persons who are not nationals of the country of any of the parties to the arbitration proceedings.
33.6 If the two arbitrators appointed by the Parties fail to agree on the appointment of the third arbitrator within thirty(30) days of the appointment of the second arbitrator and if the Parties do not otherwise agree the Secretary General of Permanent Court of Arbitration at Hague may at the request of either Party and in consultation with both, appoint the third arbitrator who shall not be a national of the country of any Party.
33.9 Arbitration proceedings shall be conducted in accordance with the UNCITRAL Model Law on International Commercial Arbitration of 1985 except that in the event of any conflict between the rules and the provisions of this Article 33, the provisions of this Article 33 shall govern.
33.10 Notwithstanding anything to the contrary contained in Article 30, the right to arbitrate disputes and claims under this Contract shall survive the termination of this Contract.
33.12 The venue of conciliation or arbitration proceedings pursuant to this Article unless the parties otherwise agree, shall be Kuala Lumpur and shall be conducted in English language. Insofar as practicable the parties shall continue to implement the terms of this contract notwithstanding the initiation of arbitration proceedings and any pending claim or dispute."

The agreement related to the Pre-BALCO period and therefore the law as stated in Bhatia International applied to it, that is, Part I of the Arbitration & Conciliation Act, 1996 (1996 Act) applied even to foreign arbitrations, unless excluded expressly or impliedly. 

Disputes arose between the parties and the same was referred to arbitration. The arbitral proceedings were held in Kuala Lumpur and the award was made and signed at Kuala Lumpur and was against the Union of India. The Union of India challenged the award u/s 34 of the Indian Arbitration & Conciliation Act, 1996 (1996 Act), which was dismissed as Part I, including S. 34, was not applicable since the place of arbitration was Kuala Lumpur. A review petition filed against the dismissal was also rejected. On appeal to a Division Bench of the Delhi High Court, the matter was dismissed. The Court's reasoning is quoted below:

"The said contract does not specifically mention the place or seat of arbitration. But, it is clear that the award was made at Kuala Lumpur. It is also clear that the UNCITRAL Model Law, 1985 is applicable. As already indicated above, Article 20(1) of the UNCITRAL Model Law, 1985 makes it clear that the parties are free to agree on the place of arbitration, failing which, the place of arbitration shall be determined by the arbitral tribunal having regard to the circumstances of the case, including the convenience of the parties. There is no express determination of the place of arbitration by the arbitral tribunal. However, the arbitration proceedings were conducted at Kuala Lumpur and the award has been made and signed at Kuala Lumpur. Because of Article 31.3 of the UNCITRAL Model Law, 1985, the date of making the award and the place of arbitration as determined in accordance with Article 20(1) is required to be stated in the award. Since there is no mention of any dispute with regard to the place of arbitration in the award made by the Arbitral Tribunal, it can safely be presumed that the award having been made at Kuala Lumpur, the place of arbitration as distinct from the venue of the arbitration, would also be Kuala Lumpur."

On facts, the court found that Part I of the 1996 Act was impliedly excluded, and therefore dismissed the appeal. Union of India appealed to the Supreme Court, whose decision is summarised below:
  • The decision in Sumitomo Heavy Industries was applicable in the context of the Arbitration Act, 1940 and would have no application in respect of the 1996 Act (Para 8).
  • The arbitration clause has to be properly construed to find out if the arbitration clause determines the seat or not (para 17). 
  • As a matter of principle, Part I could be excluded if, on facts, the juridical seat is outside India or the law governing the arbitration agreement is a law other than Indian law , as was held in Union of India v. Reliance Industries Ltd. (2015) 10 SCC 213 (Reliance II)(Para 18).
  • In IMAX Corporation (2017) 5 SCC 331, the Supreme Court held that the parties chose ICC arbitration and left the choice of seat to the ICC, which consulted the parties and chose ICC as the seat. The relevant awards were made in London. Therefore, the court concluded that Part I was excluded (Para 20).
  • In Roger Shashoua (2017) 14 SCC 722,  the Supreme Court held that where the parties had chosen a venue and there was something else the court has to determine whether these can be interpreted to mean a choice of juridical seat. In that case, since London was also the choice of the parties of the courts, London was decided to be the jurisdiction (Para 21).
  • The arbitration clause has to be read in a holistic manner to determine the jurisdiction of the court (Para 23).
  • If there is a mention of venue and something else is appended thereto, depending on the nature of the prescription the court can come to a conclusion as to the implied exclusion of Part I (Para 23).
  • UNCITRAL Model Law on International Commercial Arbitration 1985 which is applicable as per the agreement provides that the place of arbitration is to be determined by the arbitral tribunal (Para 27). Further Article 31(3) requires the tribunal to state in the award the date and place of the arbitration as determined under Article 20(1)(Para 29)
  • The parties had not chosen the seat and the arbitral tribunal was therefore required to determine the arbitral tribunal considering the convenience of the parties and the tribunal is clearly obligated to state the same in the award (Para 31).
  • Determination requires a positive act but the arbitrator held the meeting at Kuala Lumpur and passed the award. This does not amount to determination. The sittings held at various places are relatable to the venue and cannot be equated with the seat. (Para 32).
  • When the place is stated it is equivalent to seat "[b]ut if a condition precedent is attached to 'place', the condition precedent has to be satisfied so that the place can become equivalent to seat. In the instant case, as there are two distinct and disjunct riders, either of them have to be satisfied to become a place." (Para 33).
  • There is no determination here as determination signifies expressive opinion, as per Law Lexicon and Black's Law Dictionary.  (Para 33).
  • A venue can become a seat if one of the conditions precedent is satisfied and does not assume the status of seat. In the present case therefore Kuala Lumpur is not the seat of or place of arbitration and the interchangeable use cannot apply (Para 33). 
On the basis of the aforesaid reasoning, the Supreme Court held that Part I applied and Indian courts had jurisdiction. Consequently, the Supreme Court set aside the Delhi High Court's decision and remanded back the matter to the Delhi High Court to decide the Section 34 petition.

Comments

It is submitted that the reasoning and the eventual conclusion of the three Judge Bench of the Supreme Court consisting of Dipak Mistra, CJI, AM Khanwilkar & Dr. DY Chandrachud, JJ. are not correct. At the outset, this decision cannot be and should not be read as a general proposition regarding the rules of choice of seat in the absence of an expression determination thereof  in the BALCO regime. This should have a restricted application only regarding pre-BALCO regime: the ratio is only regarding an arbitration clause to which BALCO did not apply. Why? BALCO (2012) applied only prospectively.

Before we go into the detailed reasoning, we wish to draw the attention of the readers to these observations in the judgement:  

"When a 'place' is agreed upon, it gets the status of seat which means the juridical seat. We have already noted that the terms 'place' and 'seat' are used interchangeably. When only the term 'place' is stated or mentioned and no other condition is postulated, it is equivalent to 'seat' and that finalises the facet of jurisdiction. But if a condition precedent is attached to the term 'place', the said condition has to be satisfied so that the place can become equivalent to seat. In the instant case, as there are two distinct and disjunct riders, either of them have to be satisfied to become a place... The said test clearly means that the expression of determination signifies an expressive opinion. In the instant case, there has been no adjudication and expression of an opinion. Thus, the word 'place' cannot be used as seat. To elaborate, a venue can become a seat if something else is added to it as a concomitant. But a place unlike seat, at least as is seen in the contract, can become a seat if one of the conditions precedent is satisfied. It does not ipso facto assume the status of seat."

The above observation treats the term 'seat' and 'place' as two different concepts. Seat is place. Period. [see, Gary Born, International Commercial Arbitration 20152 (2014)- "it is important to distinguish between the “seat” of the arbitration (sometimes referred to as the “place” of the arbitration)".] UNCITRAL has a tradition of using the term 'place' to signify seat. Nothing more nothing less. Therefore, the observations in the first few sentences quoted above regarding conditions precedents and place are completely wrong and have been rendered without considering the evolution of international commercial arbitration and the UNCITRAL instruments, including the UNCITRAL Model Law based on which Section 21 of the 1996 Act is based. See, this link and the links provided under the head "Seat of Arbitration for a discussion regarding the use of the term "place" in UNCITRAL instruments.

At the cost of making this post lengthier, we quote some of the discussions held in the UNCITRAL during the revision of its Arbitration Rules. The then prevailing UNCITRAL Arbitration Rules, 1976, like our 1996 Act, employed the term 'place' to signify the arbitral seat. In its 45th Session, the Working Group discussed whether the  term should be substituted with "seat':

"88. A proposal was made to replace the words “place of arbitration” in article 16, paragraphs (1) and (4) with words such as “the seat of arbitration” or “the juridical seat of arbitration”. Reservations were expressed as to whether the proposed words would in fact improve the understanding of the provision. It was observed that users were often unaware of the legal consequences attached to the term “place of arbitration”. It was suggested that a reference to the “seat of arbitration” could signal the legal implications of that notion and could differ from the physical place where certain elements of the arbitral procedure were carried out or where an arbitrator might sign the award." Report of the Working Group on Arbitration and Conciliation on the work of its forty-fifth session A/CN.9/614

Ultimately the proposal to change the terminology was not retained as the usage of 'seat' was inconsistent with other UNCITRAL instruments such as the Model Law. Report of the Working Group on Arbitration and Conciliation on the work of its forty-fifth session A/CN.9/614That being the history of the use of the term 'place', the observations quoted in Para 33 of the judgement relating to 'place' are wholly wrong. 

Another error that the judgement suffers from is importing the requirement into the Model Law that place of arbitration has to be expressly determined. It need not be expressly stated or expressly determined. To support its conclusion that 'determination' signified 'expressive opinion', the Supreme Court cited Ramanatha Aiyer's Law Lexicon and Black's Law Dictionary. Both these works cited court decisions in totally different contexts. 

Aiyer's Law Lexicon cited the decision of the Supreme Court in Jaswant Sugar Mills Ltd. v. Lakshmi Chand AIR 1963 SC 677, which dealt with the meaning of the term "determination" in the context of Article 136 of the Constitution of India and had nothing to do with arbitration, let alone the interpretation of the term in the context of UNCITRAL instruments. Black's Law Dictionary cited the decision Dyken Joint Venture v. Van Dyken 279 N.W.2d 459. Nowhere in the decision does the Wisconsin Supreme Court define "determination". Even the use of the term in the judgement was in the context of interpreting a statute and this had nothing to do with "determination" in the context of international commercial arbitration, much less the UNCITRAL instruments. 

For the time being let us assume that the arbitration tribunal did not decide on the seat. What happens if neither the parties chose the seat nor the tribunal determined it? UNCITRAL's Digest on the Model Law states the following:

"Article 20 does not provide for the situation where an arbitral tribunal fails to make such a determination. If the place of arbitration is neither agreed upon by the parties, nor determined by the arbitral tribunal, the courts might have to determine the place of arbitration. In such a case, it was found that the effective place of arbitration, i.e. the place where all relevant actions in the arbitration have taken place or, if this cannot be determined, the place of the last oral hearing, should be the place of arbitration."

One would notice that not a single prominent work  on international commercial arbitration was cited in the Supreme Court's judgement, which is surprising considering Supreme Court's previous practice of citing from many major commentaries on the subject. Had it looked for such authorities, it would have found the the Model Law Digest cited the decision of the German Court (CLOUT case No. 374-also reproduced under CLOUT case No. 408) [Oberlandesgericht Düsseldorf, Germany, 6 Sch 02/99, 23 March 2000-link]. The decision partially supports the decision of the Supreme Court in the instant case but goes on to reach the opposite result based on another reasoning. The relevant portion of the decision is quoted here: 


"If the parties have not agreed on a place of arbitration, such place is determined by the arbitral tribunal.The mere mentioning of a geographical place in the arbitral award can not be understood as a determination. If neither the party nor the arbitral tribunal has determined the place of arbitration, search place is fixed by reference to the "effective place of arbitration" or, by reference to the place of arbitration the last oral hearing."

Note that in this decision the court holds that the "mere mentioning of a geographical place in the arbitral award" cannot be understood as a determination but then goes on to hold that if  neither the party nor the tribunal has determined the place of arbitration, the place is fixed by reference to the effective place of arbitration or by reference to the place of the last oral hearing. It appears on facts that the hearings were held in Kuala Lumpur and therefore even by this judgement, the effective place of arbitration and the place of the last oral hearing were in Kuala Lumpur, the seat should have been Kuala Lumpur. 

It is submitted that the German judgement is erroneous in its decision that mentioning of the geographical place cannot be a determination. So is the Supreme Court in reaching the same conclusion. Let us see why. 

Section 20(1) states: "The parties are free to agree on the place of arbitration. Failing such agreement, the place of arbitration shall be determined by the arbitral tribunal having regard to the circumstances of the case, including the convenience of the parties." Section 20(1) provides that in case parties do not agree on the place, the tribunal shall determine the place having regard to the circumstances of the case, including the convenience of the parties. In the instant case, there was no express choice by the parties. It appears that the hearings were held in Kuala Lumpur. It also appears that the tribunal did not expressly determine the place. But is this necessary? In other words, does Section 20(1) or any other provision in the Model Law require the tribunal to decide the place expressly? Ideally, it should. But what if not? 

Nowhere does the Model Law require the tribunal to decide expressly the place. It cannot be presumed that the absence of such express determination could mean that the tribunal did not determine the place. Even assuming that the tribunal committed a procedural error by not determining the place, would it not amount to a waiver of the right to object later as provided in Article 4 of the Model Law? (Article 4 reads: "A party who knows that any provision of this Law from which the parties may derogate or any requirement under the arbitration agreement has not been complied with and yet proceeds with the arbitration without stating his objection to such non-compliance without undue delay or, if a time-limit is provided therefor, within such period of time, shall be deemed to have waived his right to object."). It appears that the parties did not object to the purported non-express designation of the seat.

Article 31(3) of the Model Law provides: "The award shall state its date and the place of arbitration as determined in accordance with article 20 (1). The award shall be deemed to have been made at that place." Note that Article 31(3) talks of "determination in accordance with article 20 (1)" and 20(1) does not talk about express determination. Given Article 4 and the lack of any objection and the fact that the parties are deemed to have known about the mandatory requirement regarding place in Article 31(3), would it not be reasonable to suggest that the parties were completely agreeable to the tribunal expressly stating (and perhaps determining) the seat in the arbitral award? Interestingly, in Para 19 of the decision of the Delhi High Court in the instant case, the Division Bench makes a similar point: "Since there is no mention of any dispute with regard to the place of  arbitration in the award made by the Arbitral Tribunal, it can safely be presumed that the award having been made at Kuala Lumpur, the place of arbitration as distinct from the venue of the arbitrationwould also be Kuala Lumpur."

The purpose of Article 31(3) can be culled out from the Travaux Preparatoires of the Model Law, especially, A/40/17 - Report of the United Nations Commission on International Trade Law on the work of its eighteenth session: "254... there was a basic difference between the place stated on the award being deemed to be the place of the award and the date stated on the award being deemed to be the date of the award. The former is an irrebuttable presumption to assure the territorial link between the award and the place of arbitration. The latter must be rebuttable, since the arbitrators, as well as the parties, might have reasons for stating the date of the award to be earlier or later than the date it was actually rendered." 

Thus the effect of the insertion of the place as Kuala Lumpur in the award assured a territorial link between the award and Kuala Lumpur. Therefore, coming back to the German case, in view of the above Report, the decision of the German court is wrong and so is the decision of the Supreme Court.

Let us now look at the ex post implications of the Supreme Court's decision. For one, in the instant case, the Supreme Court has concluded that the designation by the tribunal of Kuala Lumpur was not a determination regarding the place of arbitration. This means that the Supreme Court has already concluded that the arbitral award is defective in that it has not complied with the mandatory requirement in Article 21(1) read with Article 31(3) relating to expressly declaring the place of arbitration. Would this alone be a ground to set the award aside would have to be decided by the Delhi High Court.

The Supreme Court concluded that the mere choice of foreign venue is not sufficient for presuming a foreign seat/ place. Three comments are worth noting here: 

(1) The present case was not simply a case of mere choice of foreign venue. There were many more things to the arbitration clause: Parties had agreed to choose a set of non-national arbitration rules in the form of the UNCITRAL Model Law. The appointing authority was to be the Secretary General of the Permanent Court of Arbitration. Weren't these choices sufficient to reach a conclusion of implied exclusion (Mere choice of a foreign appointing authority as opposed to Indian meant that Indian courts as the appointing authority under Section 11 of the 1996 Act was impliedly excluded.).

(2) In the context of post-BALCO decisions, the conclusion reached on the same facts would be different because Part I would not apply in foreign arbitrations. Considering the factors mentioned in point (1) above along with the choice of foreign venue, the arbitration in the BALCO regime would be foreign. 

(3) Many times, parties to the contract are either ignorant of cutting edge distinctions between seat and venue. Often they do not obtain legal advice and even if they do, some are not conversant with the implications of the usage of venue instead of seat especially if the native language of the parties is not English. Sometimes, the parties postpone the agreement on particular clauses such as the seat to after disputes have arisen because they are not able to agree on the place. Contract negotiations take place in a dynamic environment and courts should be conscious of these aspects while construing arbitration clauses and should not adopt an overly technical approach.

Lastly, the first para of the Supreme Court's decision states that the Single Judge who heard the Section 34 petition dismissed the same vide judgement dt. 09.07.2015 for the reason that "in view of the terms of the agreement and the precedents holding the field, the Indian courts have no jurisdiction to entertain the application." This is factually untrue. OMP No. 693/2013 was filed by Union of India challenging the arbitral award. The matter was heard and the court vide its judgement dt. 09.07.2015 did not accept any preliminary objection nor did it hold that Indian courts did not have any jurisdiction. The petition was in fact withdrawn. Thereafter a Review Petition was filed by the Union of India and the review petition was dismissed since the petition under Section 34 was withdrawn. Even at this stage, the Single Judge did not pass any order on merits. It was only the Division Bench that decided that Indian courts could not exercise jurisdiction since Part I was impliedly excluded. Consequently, Para 2 of the decision of the Supreme Court is also factually erroneous in that the Division Bench did not concur with the Single Judge's view on jurisdiction and applicability of Part I because no view was expressed by the Single Judge!

All said and done, the case is an apt example as to why arbitration agreements should be drafted precisely and should include the choice of seat or place of the arbitration.

Friday, October 5, 2018

Liquidated Damages under Indian Contract Law between 1872 & 1899

On 29 September 2018, we did a brief article review of S. Swaminathan’s erudite paper in the Chinese Journal of Comparative Law (link-subscription required) De-inventing the Wheel: Liquidated Damages, Penalties and the Indian Contract Act, 1872, 6 Chinese Journal of Comparative Law 103-127 (2018). This post is in respect of one of the topics addressed in the paper.

An important argument in the paper is that the 1899 amendment brought in the dichotomy of liquidated damages-penalty into the Indian Contract Act, 1872, before which such a dichotomy never existed. Although this view is more or less correct, it appears from a perusal of the decisions rendered prior to 1899 that the judges ended up judicially incorporating the dichotomy in their decisions. 

Section 74 as it Stood Originally

The original Section 74 was substituted by Section 4 of the Act VI of 1899. Para 1 of Section 74 as it originally stood read as below (Para 2 did not undergo any substantial amendment):

Title to compensation for breach of contract in which a sum is named as payable in case of breach- When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named.”

One of the chief aims of the original Section 74 was to do away with courts inquiring as to whether the amount named is liquidated damages or a penalty. Swaminathan argues that this did not happen primarily owing to the amendments in 1899 which introduced the dichotomy:

Just how did the exact opposite of what the drafters had envisaged come to be the state of the law and this, after they had been so careful about wanting to avoid the troublesome liquidated damages-penalty dichotomy?… The single most important contributing factor in bringing this about, it will be hypothesized, was an ambiguity unwittingly introduced by an amendment to section 74 in 1899 by a select committee headed by the ace draftsman Mackenzie Chalmers… However, the effect of the introduction of the word ‘penalty’ in the provision in sharp contrast to the neologisms used by the original provision was to prove troublesome. It was to create the misleading (and unintended) impression that the English concept of ‘penalty’ was being sought to be introduced into Indian law. Once penalty was in, liquidated damages was but not even a step away.”

“Controversy Surrounding “Sum is Named in the Contract”

The author also acknowledges that the way in which the original Section was drafted did not help matters and referred to the more controversial issue then regarding whether clauses providing for increased interest on account of default could be covered under the original Section 74:

"The phrase ‘sum named in the contract’ ostensibly meant that the provision applied only to in solido sums, thus leaving out stipulations for variations of interest, acceleration clauses which affected payment schedules rather than sums, and payments in specie. This ambiguity led to a great divergence of opinion among Indian courts on the applicability of section 74 to such clauses. A good fraction of the litigation on section 74 involved such stipulations.”

This is correct. A perusal of the decisions between 1872 and 1899 reveal this aspect. There were divergent views of various High Courts on the question as to whether the original section applied even to a stipulation that could be categorized penalty although the amount of penalty was not “named” in the contract. See, for instance, H. Mackintosh v. Hunt (1877) ILR 2 Cal 202, where the Calcutta High Court held:

We are of opinion that the contract to pay interest at 10 per cent, per mensem, if the principal sum of Rs. 400 were not paid on September 6th, the duo date of the promissory note, is not in the nature of a penalty… In such a provision there is nothing in the nature of a penalty more than there is in a provision, that the promissory note shall bear interest from the day of its date. The case seems to us to differ wholly from that class of cases in which a certain sum is agreed to be paid on a breach of contract, and therefore Section 74 of the Contract Act (IX of 1872) does not apply.”

A Full Bench of the Calcutta High Court upheld this view about twenty two years later in Deno Nath Santh v. Nibaran Chandra Chuckerbutty and Ors. MANU/WB/0158/1899 by holding that “this is not a sum named in the contract as the amount to be paid in case of such breach, and Section 74 does not apply.” There were equally a good number of cases where the fine distinctions between such clauses were made and contra view was upheld. See, for instance H. Mackintosh v. C. Crow and Anr. (1883) ILR 9 Cal 689 and a decision of the Full Bench of the Calcutta High Court in  Kala Chand Kyal v. Shib Chunder Roy I.L.R. 19 Cal. 392 (FB): MANU/WB/0013/1892.  It must also be noted that in cases where the courts held that Section 74 were not applicable, the debtor did not stand unprotected and could raise defences available to him in equity. See, for instance, H. Mackintosh v. Hunt (1877) ILR 2 Cal 202, Mackintosh v. Wingrove (1879) ILR 4 Cal 137 and Ram Prasad And Ors. v. Lalli (20 July 1886) (1887) ILR 9 All 74. Nevertheless, considering the decision of the Full Bench in Deno Nath (above), we are not sure the remedy was efficacious.

Now, coming back to Swaminathan’s article, the author argues: “Unsure about the applicability of this provision to such cases, Indian courts increasingly began to fall back on the English law to decide these cases.” The author seems to suggest from this argument that owing to the controversy regarding whether enhanced interest clauses were “sum named in the contract”, English law were relied on to decide those cases. The author’s argument that courts relied on English legal principles were the principles of equity. 

If the author's argument that the dichotomy was brought back into Indian law post 1899, in an ideal scenario, courts would never have referred to the dichotomy or decided the cases without referring to the “liquidated damages” and “penalty” nomenclatures. However, as we would see in the remaining portions of this post, the dichotomy never ceased to haunt Indian law post-1872.

Decisions Construing the Original Section 74 Pre-1899

In one of the earliest cases decided after the Indian Contract Act, 1872, H. Mackintosh v. Hunt (1877) ILR 2 Cal 202, the Calcutta High Court had to decide whether the clause was hit by Section 74. The Calcutta High Court held: “We are of opinion that the contract to pay interest at 10 per cent, per mensem, if the principal sum of Rs. 400 were not paid on September 6th, the duo date of the promissory note, is not in the nature of a penalty… The case seems to us to differ wholly from that class of cases in which a certain sum is agreed to be paid on a breach of contract, and therefore Section 74 of the Contract Act (IX of 1872) does not apply.” (emphasis supplied).  Notice above the use of “penalty” while referring to Section 74.

There are several other judgements which are in line with the above. Some of them are cited below along with the relevant observations of the court:

H. Mackintosh v. C. Crow and Anr. (1883) ILR 9 Cal 689: MANU/WB/0037/1883: “This section, it will be observed, does away with the distinction between a penalty and liquidated damages and this must be borne in mind in dealing with cases decided before the Contract Act, many of which turned upon this distinction. Under this section, whether a sum would formerly have been held a penalty or liquidated damages, if it be named in the contract as the amount to be paid in case of breach, it is to be treated, much as a penalty was before, as the maximum limit of damages.” Now, if the stipulated sum was to be treated as a penalty, it should be so determined and what followed was to import the test in English law. See, also Sungut Lal vs. Baijnath Roy and Anr. (17.06.1886 - CALHC) (1886) ILR 13 Cal 164: MANU/WB/0146/1886, where the dichotomy seems to have been used although the court recognised that Section 74 did away with it. Sundar Lal v Banke Behari (28.06.1893 - ALLHC) : MANU/UP/0058/1893 also imported the dichotomy although the Full Bench of the High Court held that the clause involved was not one to which Section 74 applied. Similar is the decision of Ram Prasad And Ors. v. Lalli (20 July 1886) (1887) ILR 9 All 74 where although the Allahabad High Court held that Section 74 did not apply nevertheless recognised the concept of penalty

See also, Dilbar Sarkar vs. Joysri Kurmi and A.M. Dunne and Ors. (12.08.1898 - CALHC) : MANU/WB/0261/1898 (“Undoubtedly, sec. 74 of the Contract Act has clone (sic done) away with the distinction between a penalty and liquidated damages and although, generally speaking, the distinction between these two classes of damages is fine, yet it is desirable to bear in mind that in some cases there is a broad distinction, In this case undoubtedly the sum agreed upon by way of damages was agreed upon as a penalty.”

It could thus be observed that importation of the dichotomy into Indian jurisprudence was not a phenomenon merely attributable to the 1899 amendment. As these cases, and many more, go to show, notwithstanding the doing away of the distinction, the dichotomy never went away. The implications of this inference may have an impact on the villainous portrayal by the authorof the 1899 amendment as having brought back the dichotomy. The 1899 amendment at the most normalized the importation of the dichotomy, which never went away, except in a miniscule number of cases.

Cases Decided on the Basis of the Original Section 74 Without Importation of the English principles

On the other side of the spectrum is the interesting case of Nait Ram vs. Shib Dat and Ors. (15.12.1882 - ALLHC) : MANU/UP/0103/1882. The suit was for the recovery of the principal amount of Rs. 200 issued under bond to the defendant and for Rs. 400 towards liquidated damages for breach of the bond. The plaintiff did not lead any evidence towards loss and the munsiff’s court applied Section 74 and declared the amount claimed towards LD as excessive thereby considerably reducing the claim towards liquidated damages. On appeal, the appellate court termed the decision regarding assessment of liquidated damages as erroneous and held Rs. 100 as LD to be reasonable.

On further appeal, the Division Bench of the Allahabad High Court recognised the legislative intent behind enactment of Section 74: to eliminate the LD-penalty dichotomy: “The section appears to have been introduced to obviate the difficulties which exist in distinguishing liquidated damages, from penalty under the English Law and the effect of it is, that the Court are not bound to award the entire amount of damages agreed upon by the parties in anticipation of the breach of contract. The only restriction is that the Court cannot decree damages exceeding amount previously agreed upon by the parties.”

On how reasonableness has to be determined, the court held: “The discretion of the Court in the matter of reducing the amount of damages agreed upon is left unqualified by any specific limitation though of course the expression "reasonable compensation" used in the section necessarily implies that the discretion so vested must be exercised with care, caution, and on sound principal (sic principles).”

On how the discretion has to be exercised, the court’s decision deserves summarizing:
  • Damages should be commensurate with the injury sustained.
  • It should be assessed with the view to restoring the advantage to the plaintiff that he might have received if the contract had been performed.
  • Where it is impossible to arrive at the exact damages, courts award the amount named, and nothing more.
Thereafter, the court held that this was not a case where it was impossible to arrive at the damages. On the assessment of damages, the court basically repeated the manner in which damages would be proved in a claim for general damages under Section 73. 

Another similar decision is that of Brahmaputra Tea Co. Ld. v. E. Scarth (MANU/WB/0175/1885 : (1885) ILR 11 Cal 545). The defendant entered into an agreement with the plaintiff to serve as an assistant tea planter for a salary. Clause 8 of the agreement named a sum as damages in case of breach of the agreement. The plaintiff initiated a suit to recover, inter alia¸ the named sum from the defendant as per clause 8 of the agreement. The plaintiff did not lead any evidence in the trial on the actual loss suffered and merely relied on the amount named in clause 8 of the agreement. However, the trial court held that the plaintiff was entitled to an amount that was far lesser than the amount stipulated in the agreement. On appeal, a two judge Bench of the Calcutta High Court consisting of McDonell and Macpherson, JJ was of the view that it was not necessary for the plaintiff to prove damages or loss. The Bench was of the opinion that the trial court erred in reducing the amount of compensation. It held:

“…the agreement by the defendant himself, so he knew full well what he was doing and what risk he was incurring, and, so far as we can see, there was no reasonable or sufficient ground for his act. No doubt the Court has a discretion to fix what it considers reasonable compensation; but when the parties have already agreed among themselves as to what the penalty should be, we think the Court should not, in fixing the compensation, wholly ignore the amount agreed on, unless this is, on its face, wholly unreasonable with reference to the position of the parties and the breach provided against.”

The court felt that the Liquidated Damages named in the agreement was not “wholly unreasonable” and must have been agreed between the parties after taking into consideration to all the circumstances attending the consequences of breach. However, the court doubted if the amount named in the agreement could be considered as reasonable “in the absence of any proof to the contrary”. Consequently, the court exercised its discretion in the matter and awarded a sum which was approximately half-way between the amount specified in the judgement of the trial court and the amount named in the agreement.

Thus, it would seem that even from the beginning, courts were grappling with the inconsistency in the text of the statute: on the one hand, the plaintiff was not required to prove the actual loss caused by the breach and, on the other, the court could grant only reasonable compensation for which it had to allow the parties to lead evidence on the reasonableness of the amount named in the contract. A way of resolving it was to simply suggest, like Nait Ram that damages should be proved akin to a claim under Section 73. Another way was to award damages in the absence of proof as a fraction (or percentage) of the amount in the contract as it happened in Brahmaputra Tea Co. in 1885 (see above) and in Construction and Design Services vs. Delhi Development Authority MANU/SC/0099/2015, one hundred and thirty years later.

Closing Remarks

In the light of Cavendish Square, is it not the time to move on and bring about a more nuanced and predictable model of determination of Liquidated Damages? The reasonableness standard does not offer certainty and inevitably allows promisors to challenge the imposition in courts regularly.  

Thursday, October 4, 2018

Critique of the Specific Relief (Amendment) Act, 2018

Over at Obiter Dicta, the respected Dr. Nilima Bhadbhade, one of the foremost experts in India on Contract and Specific Relief law, has penned a comprehensive critique on the Specific Relief (Amendment) Act, 2018. The post by Dr. Bhadbhade primarily argues that the amendment was a case of hurried legislation and was a comprehensive deviation from the Expert Committee Report. The post notes that the Ministry of Law & Justice did not publish the report but the same was made available through the RTI Act. This was probably a reference to our post making the Report public pursuant to an RTI application by us.

We had several posts in this blog (here, here, here and here) and elsewhere critiquing one particular aspect: the way in which the amendment affected the balance maintained by contract law between the interests of the victim of the breach and the perpetrator of breach. The post by Dr. Bhadbhade confirms the validity of the criticisms made, and coming from a person with immense expertise and who was a part of the Expert Committee, the Government should take it seriously to explore the option of amending the amendment to ensure that legitimate criticisms of the Act are addressed. 

Monday, October 1, 2018

Tribunal Secretaries & the Proposed Amendments to the Indian Arbitration Law

The Arbitration and Conciliation (Amendment) Bill, 2018 has been passed in the Lok Sabha and is likely to be discussed in the Rajya Sabha in the forthcoming Parliamentary session. The amendments seek to establish India as a robust centre for international arbitration. Of the many aspects that the Bill has missed out, one of the crucial aspects of international arbitration that the Bill has failed to address is the issue relating to tribunal secretaries. 

Tribunal secretaries are considered as an integral part of international arbitrations, especially with high stakes and complexities involved.  They have been regarded as the fourth arbitrator and yet the appointment, functioning and other aspects relating to tribunal secretaries are hardly addressed by the amendment. Given that the role and functioning of tribunal secretaries is a grey area, it would do well for India to address this statutorily. Hence, the following amendments are suggested (sincere thanks to Dr Shaswat Bajpai for his comments on the topic)

Inclusion of Fee to Tribunal Secretaries in Costs of Arbitration

The definition of "costs" in Section 31A should include the fees to tribunal secretaries as well. This would mean that the arbitral tribunal will have a lien over the award under Section 39(1) if the fee of the tribunal secretaries remain unpaid. The following amendments are suggested in Section 31A:

Explanation to Section 31A(1) which defines costs should include fees and expenses of tribunal secretaries also.  Accordingly, the phrase "tribunal secretaries" is sought to be added to clause (i) of the explanation as below:

"Explanation: For the purpose of this subsection, "costs" means reasonable costs relating to
i) the fees and expenses of the arbitrators, tribunal secretaries, Courts and witnesses;
(ii) legal fees and expenses;
(iii) any administration fees of the institution supervising the arbitration; and
(iv) any other expenses incurred in connection with the arbitral or Court proceedings and the arbitral award."

Immunity to Arbitrators to Extend to Tribunal Secretaries

The 2018 Amendment Bill proposes to introduce a provision on immunity of the arbitrators in the firm of Section 42B. This immunity should be extended to tribunal secretaries as well. It is suggested that the phrase “or the tribunal secretary” is added after “the arbitrator” in the proposed Section 42B.

An amended Section 42B as per the above suggestion would read as below:

No suit or other legal proceedings shall lie against the arbitrator or the tribunal secretary for anything which is in good faith done or intended to be done under this Act or the rules or regulations made thereunder."

Arbitration Promotion Council to Take Steps to Recognise Professional Institutes Providing Accreditation of Tribunal Secretaries

Section 43D proposed to be introduced vide the 2018 Amendment Bill lays down the functions of the Arbitration Promotion Council of India. It does not deal with tribunal secretaries. While conducting training programmes for tribunal secretaries could be covered under Section 43D(2)(i), Section 43D is silent on tribunal secretaries. From a perusal of Section 43D, it appears that the Arbitration Promotion Council of India is not tasked with directly accrediting arbitrators. Section 43D(2)(b) provides for recognition of professional institutes which accredit arbitrators. The Council, then, should also recognize professional institutes accrediting tribunal secretaries. To this end, the phrase “and tribunal secretaries” should be added after “arbitrators” in Section 43D(2)(b).

The proposed Section 43D(2)(b) would read as below:

“(2) For the purposes of performing the duties and discharging the functions under this Act, the Council may—
(b) recognise professional institutes providing accreditation of arbitrators “and tribunal secretaries”;

General Norms Applicable to Arbitrators in Eighth Schedule Should Apply Mutatis Mutandis to Tribunal Secretaries

Section 43G of the 2018 Bill provides that the qualifications, experience and norms for accreditation of arbitrators shall be as specified in the Eighth Schedule. Eighth Schedule sought to be introduced by the 2018 Bill lays down the qualifications, experience and norms for accreditation of arbitrators. The norms should apply to tribunal secretaries also.

Although it may be unreasonable to provide for experience requirements for tribunal secretaries, it is imperative that appointment of trained tribunal secretaries is encouraged. To that end, a tribunal secretary to be eligible for appointment must have at least undergone training from recognized institutions.

Following amendments are suggested:

The phrase “and tribunal secretaries” should be added after “of arbitrators” in Section 43G. Section 43G would then read:

“The qualifications, experience and norms for accreditation of arbitrators and tribunal secretaries shall be such as specified in the Eighth Schedule:

Provided that the Central Government may, after consultation with the Council, by notification in the Official Gazette, amend the Eighth Schedule and thereupon, the Eighth Schedule shall be deemed to have been amended accordingly.”

At the end of the Eighth Schedule, the following are to be added:

Qualifications of Tribunal Secretary

A person shall not be qualified to be a tribunal secretary unless he is trained and certified as such by a professional institute recognised by the Arbitration Promotion Council of India.

General Norms Applicable to Tribunal Secretary

The general norms applicable to arbitrator shall apply mutatis mutandis to tribunal secretary.”

Model Rules Applicable to Appointment and Functioning of Tribunal Secretaries

The current law is silent on the rules regarding the appointment and functioning of tribunal secretaries. Hence, it is proposed that a new Section 15A is added to provide detailed rules that would apply in default for appointment of tribunal secretaries unless parties agree otherwise. Detailed rules in this regard could be contained in a Ninth Schedule. Similar to Section 11A, the Central Government will be empowered with the right to amend the Ninth Schedule.

The provisions proposed will be as below:

15A. Tribunal Secretaries.-

(1) The parties are free to agree on the number, qualifications, procedure for appointment and functions of tribunal secretaries to the arbitration proceedings.

(2) Failing any agreement referred to in sub-section (1), the Ninth Schedule shall guide the parties and the arbitral tribunal in the appointment and functioning of tribunal secretaries in the arbitration proceedings.

(3) If the Central Government is satisfied that it is necessary or expedient so to do, it may, by notification in the Official Gazette, amend the Ninth Schedule and thereupon the Ninth Schedule shall be deemed to have been amended accordingly.

(4) A copy of every notification proposed to be issued under sub-section (3), shall be laid in draft before each House of Parliament, while it is in session, for a total period of thirty days which may be comprised in one session or in two or more successive sessions, and if, before the expiry of the session immediately following the session or the successive sessions aforesaid, both Houses agree in disapproving the issue of the notification or both Houses agree in making any modification in the notification, the notification shall not be issued or, as the case may be, shall be issued only in such modified form as may be agreed upon by the both Houses of Parliament.”

The Government could come up with draft model rules addressing the topics of appointment, role and functions of tribunal secretaries. If India has to achieve the salutary aim of becoming a robust centre for international arbitration, the arbitration law should reflect the best practices in international arbitration. The need of the day is a comprehensive and enabling system of international arbitration. It would do well for the Government to explore the option of introducing these amendments in the current round of reforms.