"I realise that some of my criticisms may be mistaken; but to refuse to criticize judgements for fear of being mistaken is to abandon criticism altogether... If any of my criticisms are found to be correct, the cause is served; and if any are found to be incorrect the very process of finding out my mistakes must lead to the discovery of the right reasons, or better reasons than I have been able to give, and the cause is served just as well."

-Mr. HM Seervai, Preface to the 1st ed., Constitutional Law of India.

Wednesday, April 14, 2021

Time as Essence in Construction Contracts: Need for a Comprehensive Relook

The issue of time as essence in construction contracts is controversial and is frequently litigated. The law on the subject is largely unsatisfactory. In a paper titled "The Law on Time as Essence in Construction Contracts: A Critique" published in Volume 8 Issue 1 of the RGNUL Financial and mercantile Law Review (here), the law on the subject is critically evaluated. The paper argues that the precedent on the issue, Hind Construction Contractors v. State of Maharashtra, AIR 1979 SC 720 ("Hind Construction"), was wrongly decided and requires reconsideration. It also argues that:

  • Hind Construction is no more relevant to the current times and provides incentives to inefficient contractors leading to delay in project completion; 
  • Contracting parties do not appear to have circumvented the adverse effect produced by Hind Construction through the use of appropriate language in their contracts despite various decisions following the said decision; and 
  • One of such reasons for the phenomena appears to be a lack of direction by courts as to what contracting language could constitute future courts to construe a contractual condition providing that time is of the essence as such.
Image Credits*
The paper concludes by arguing that concludes by highlighting possible contractual clauses and contract management strategies that could further party intent that time is of the essence in construction contracts notwithstanding Hind Construction and later decisions following it.

Abstract of the Paper is provided below:

"The concept of time as essence in construction contracts is a controversial topic. Even though parties routinely provide in their agreements that time is of the essence, these clauses inevitably figure in construction disputes. Arbitral tribunals and courts have mostly decided such disputes holding those clauses to be of no legal effect, mainly by relying on the decision of a three-judge bench of the Hon’ble Supreme Court in Hind Construction Contractors v. State of Maharashtra. This paper argues that Hind Construction was wrongly decided, that it is not good law and that it requires reconsideration given the changing times. The paper further notes that parties do not appear to have circumvented the adverse effect of Hind Construction. Usually, in such situations, there is a change in contracting behaviour by the use of appropriate contracting language. Perhaps, this is due to the lack of direction by courts as to what appropriate language could be used in contracts to make time as the essence of the contract. This paper concludes by suggesting possible methods by which courts and arbitral tribunals could validly enforce time-as-essence clauses."

Critique of the paper is welcome as comments to this post. Readers can also write to lawbadri@gmail.com