McLauchlan, David, Remoteness
Re-Invented? (January 31, 2010). Victoria University of Wellington
Legal Research Paper No. 3. Available at SSRN:
http://ssrn.com/abstract=1866167
"Remoteness Re-invented?" by David McLauchlan, a professor of law at the University of Wellington, discusses one of the most important cases in the recent times on damages in contract law- Transfield Shipping Inc v. Mercator Shipping Inc. (The Achilleas) [2008] UKHL 48. This blog post briefly reviews the article.
"Remoteness Re-invented?" by David McLauchlan, a professor of law at the University of Wellington, discusses one of the most important cases in the recent times on damages in contract law- Transfield Shipping Inc v. Mercator Shipping Inc. (The Achilleas) [2008] UKHL 48. This blog post briefly reviews the article.
The
Achilleas
Mercator Shipping (Mercator) was
the owner of the ship the Achilleas. Mercator and Transfield Shipping
(Transfield) entered into a time charter of the Achilleas at a daily rate of
USD 16,750 and the latest date of redelivery was May 2. On April 20, Mercator sent a notice for
redelivery between April 30 and May 2. In the meanwhile, Mercator entered into
a “follow-on” time charter (the second charter was to commence after redelivery by Transfield) with Cargill for four to six months at a daily rate
of USD 39,500. The huge difference in rates between the two charters was due to
a dramatic rise in the market rates. Cargill had an option to cancel the time
charter in case the vessel was not delivered it by May 8.
Despite the notice of redelivery,
Mercator could not redeliver the vessel by May 2. It appeared that the vessel
would be redelivered only by May 11. By May 5, it became apparent to Cargill
that the vessel could not be delivered by May 8. Instead of exercising its
right to cancel the time charter, Cargill renegotiated with Mercator to reduce
the daily rate to USD 31,500, consistent with the fall in market prices.
Mercator sued Transfield for the
difference between the original rate of USD 39,500 and the renegotiated rate of
USD 31,500 (USD 8,000) for the entire period of the time charter (four to six
months), which amounted to USD 1.4 million.
Transfield contended that that
Mercator was not entitled to the claim as the damages was too remote and that
Mercator was entitled only to the difference between the contract rate and
market rate for nine days, that is, the due date for redelivery and the actual
date of redelivery.
There were five judgements of the House of Lords some
with different reasoning but with the consistent final decision that Mercator
was not liable to the claim of USD 1.4 million as it was too remote.
Remoteness Re-Invented?
The author structured his article
in the following manner:
A. Introduction
B. Academic Debates (consisting of case comments/ articles dealing with the case/ the subject)
C. Achilleas (discussing the decisions of the courts below and the four judgements in the House of Lords)
D.Effects of the Decision
E. Conclusion
According to the author, the
decision by the House of Lords took the contract law scholars by surprise
because the arbitral awards were by arbitrators with specialized knowledge in
the field and the judgements by the High Court and the Court of Appeal were
admittedly by judges with great commercial experience. In fact, one of the
decisions in the Court of Appeal was by the renowned Rix, LJ. Nevertheless, the
House of Lords overturned the decisions of the arbitral tribunal and the lower
courts.
In Part B of the paper, the
author discusses the various academic theories surrounding the determination of
whether damages claimed was remote such as the instrumental promises theory,
agreement-centric approach and the default rule approach. After a brief
analysis, the author concludes that “from a practical point of view [the
academic debates] should not matter” as long as it is recognized that
“[r]easonable foreseeability will usually be necessary but it is certainly ‘not
sufficient for liability’”.
In Part C, the author discusses
the decision of the lower courts and judgements of by each of the five judges
sitting in the House of Lords. The author notes that the judges were ultimately
of the view that the owner was not entitled to the loss claimed but only for
what the charterer conceded as the entitlement of the owner. In Part D, the
author attempts to formulate the ratio of the majority as different reasoning
was provided by the judges of the House of Lords. The
ratio according to Mclauchlan is as follows:
“A loss may not be considered too remote even if it was of the type or kind that would have been within the reasonable contemplation of the parties as a not unlikely result of the breach. Defendants will escape liability for foreseeable loss if it cannot be reasonably be inferred that they accepted responsibility for that loss”.
The author explains that the
court’s view meant that the plaintiff could recover damages for “unusual”
losses on the basis of the knowledge of special circumstances only if it was
established from an objective point of view that the defendant had accepted the
contract with the special circumstance attached to it. The effect of the
decision, according to the author, is:
“[W]hether or not a particular kind of loss is held to be foreseeable because of imputed knowledge or actual knowledge of special circumstances, the defendant can escape liability if the court is satisfied that it would be unreasonable to infer that the defendant accepted the responsibility for that loss.”
This, according to the author is
a positive development because the judges would not longer hide behind “bland
assertions” but would have to clearly spell out how there was assumption of the
risk. The author also discusses a few categories of factors that might lead the
court to conclude one way or the other.Another possible consequence of
the judgement discussed in the article is that it courts might be reluctant to
award damages which are substantially disproportionate to the consideration
received because it may be possible to reasonably infer that the defendant
never “agreed” to bear liability for such a loss.
Case Comments on the Decision:
- Adam Kramer, ‘An Agreement-Centred Approach to Remoteness and Contract Damages’ in Nili Cohen & Ewan McKendrick (eds), Comparative Remedies for Breach of Contract (Hart Publishing, Oxford and Portland 2005) 249;
- Andrew Tettenborn, ‘Hadley v Baxendale Foreseeability: A Principle Beyond Its Sell-by Date?’ (2007) 23 J of Contract L 120;
- Andrew Robertson, ‘The Basis of the Remoteness Rule in Contract’ (2008) 28 Legal Studies 172.
- Edwin Peel, ‘Remoteness Revisited’ (2009) 125 LQ Rev 6
No comments:
Post a Comment