"I realise that some of my criticisms may be mistaken; but to refuse to criticize judgements for fear of being mistaken is to abandon criticism altogether... If any of my criticisms are found to be correct, the cause is served; and if any are found to be incorrect the very process of finding out my mistakes must lead to the discovery of the right reasons, or better reasons than I have been able to give, and the cause is served just as well."

-Mr. HM Seervai, Preface to the 1st ed., Constitutional Law of India.

Wednesday, August 1, 2018

Guest Post: Mid-Year Arbitration Review- Part III by Juhi Gupta

(Continuing with her mid-year arbitration review (see previous posts here and here), Ms. Juhi Gupta, an LL.M. graduate from Harvard Law School, has penned the third part of the series of posts on the topic. Do check out the awesome, crisp and to-the-point descriptive comment on prominent arbitration related cases decided in India in the first half of 2018. Happy reading!)

In the third of a series of posts, I review two significant Supreme Court decisions on the issue of binding non-signatories to an arbitration agreement. I have discussed the cases in slight detail as they involve different facts and circumstances that demonstrate different aspects of the issue.

Non-signatories to arbitration agreement can be referred to domestic arbitration under section 8 based on facts and circumstances; mere allegations of fraud cannot disable arbitration


Brief facts: The respondent (Rishabh Enterprises) entered into four agreements: two agreements with Juwi India that contained arbitration clauses, a sale and purchase agreement with Astonfield Renewables (hereinafter “Astonfield Agreement”) that did not contain an arbitration clause, and an equipment lease agreement with Dante Energy that contained an arbitration clause. The agreements related to the commissioning of a solar power plant in Uttar Pradesh, India.

A dispute arose between the parties wherein the respondents alleged that Dante Energy defaulted in payment of rent and that Astonfield Renewables committed fraud by inducing Rishabh Enterprises to purchase certain products under the Astonfield Agreement. Dante Energy invoked the arbitration clause in response to which the respondents filed a civil suit for fraud and misrepresentation. In response to the civil suit, the appellants filed an application under section 8 of the Arbitration Act (hereinafter “the Act”) seeking reference of the dispute to arbitration on the ground that all four agreements were inter-connected as they were executed between the same parties and pertained to the same purpose. The respondents opposed the application, contending that the matter could not be referred to arbitration while the suit for declaration that the agreements were vitiated due to fraud and misrepresentation was pending. Further, the suit only concerned fraud committed by Astonfield Renewables and Dante Energy for which a criminal case had been registered and hence, the dispute could not be referred to arbitration.

The single judge and subsequently Division Bench dismissed the section 8 application by relying on Sukanya Holdings - the Astonfield Agreement, which was the principal agreement according to them, did not contain an arbitration clause and the agreement was not inter-connected with the other agreements. Further, given serious allegations of fraud were involved, the dispute was not arbitrable. The respondents appealed against the Division Bench judgment to the Supreme Court.

Issues: (1) Were all four agreements inter-connected such that the parties could be referred to arbitration even though there was no arbitration clause in the Astonfield Agreement?; and (2) was the dispute non-arbitrable on account of the allegations of fraud or was the dispute arbitrable by taking the agreements as a commercial undertaking of the parties with a sense of business efficacy as held in Ayyasamy?

Arguments: On the first issue: the respondents argued that the Astonfield Agreement was the main agreement and the High Court’s reliance on Sukanya Holdings was correct since under Part I of the Act, parties who were not signatories to the arbitration agreement (in this case Astonfield) cannot be referred to arbitration. The appellants’ reliance on Chloro Controls was misplaced as that case was decided under Part II of the Act and did not overrule Sukanya Holdings (note: Chloro Controls held that non-signatories could be referred to a foreign-seated arbitration under section 45 of the Act in certain circumstances).
On the second issue: the appellants argued that were no serious allegations of fraud to decline a reference to arbitration. Based on Ayyasamy, they submitted that mere allegations of fraud were not sufficient to detract from the referring the matter to arbitration as per the agreement. The respondents argued that the allegations were very serious and not merely to disable the arbitration, and that the appellants were guilty of cheating the respondents from the very beginning.

Decision: The Supreme Court decided both issues in favour of the appellants and referred the parties to arbitration.

On the first issue, the Court, albeit not expressly, applied the principles laid down in Chloro Controls, such as “direct relationship to the party signatory to the arbitration agreement, direct commonality of the subject-matter and the agreement between the parties being a composite transaction” (paragraph 20; paragraph 73 of Chloro Controls). The Court concluded that the four agreements were for the single purpose to commission the solar power plant. The Court characterised the equipment lease agreement with Dante Energy as the principal agreement and after undertaking an analysis of the relevant clauses, the Court concluded that the other three agreements were ancillary agreements, which led to the main purpose of commissioning the power plant:

“Even though, the Sale and Purchase Agreement (05.03.2012) between Rishabh and Astonfield does not contain arbitration clause, it is integrally connected with the commissioning of the Solar Plant…and even though, Astonfield and appellant No.1 Ameet Lalchand Shah are not signatories to the main agreement viz. Equipment Lease Agreement (14.03.2012), it is a commercial transaction integrally connected with commissioning of [the power plant]…what is evident from the facts and intention of the parties is to facilitate procurement of equipments, sale and purchase of equipments, installation and leasing out the equipments to Dante Energy. The dispute between the parties to various agreements could be resolved only by referring all the four agreements and the parties thereon to arbitration” (paragraph 21) [emphasis supplied].

Therefore, the Court essentially concluded that since all parties were involved in a single commercial project that was executed through several agreements, they were all covered by the arbitration clause in the equipment lease agreement that was the main agreement. The Court pointed out that the Delhi High Court erred in characterising the Astonfield Agreement as the main agreement.

In this context, the Court also referred to the 2015 amendment of section 8 which amplified the relevant “party” that is entitled to seek a reference to arbitration to include all persons claiming “through or under” a party to the arbitration agreement. Further, as per the recommendations of the 246th Law Commission Report, a prima facie existence of an arbitration agreement was sufficient to refer parties to arbitration under section 8.

On the second issue, the Court concurred with the appellants’ reliance on Ayyasamy. In that case it was held that when a party wants to wriggle out of an arbitration agreement on the basis of alleged fraud, then a strict and meticulous inquiry is needed to determine whether the allegations are of a serious and complicated nature that should be addressed by the court. Further, it was pointed out that mere allegations of fraud could not preclude arbitration and it was the duty of the court to impart business efficacy to commercial transactions.

Applying Ayyasamy, the Court held that the allegations of fraud were not serious and in any event, could very well be examined by the arbitral tribunal. Even though Juwi India and Astonfield were not parties to the lease agreement, all the agreements contained clauses referring to the lease agreement and it was the duty of the Court to not merely go by the averments made in the submissions but to also adopt a commercial understanding and impart business efficacy.

Comment: The Supreme Court appears to have limited the application of Sukanya Holdings under section 8. While discussing the 2015 amendments to this provision, the Court pointed out the introduction of the section 45 language (“through or under”) and that the amendments apply notwithstanding any judicial precedent, which would arguably include Sukanya Holdings. Therefore, this judicial decision assumes immense significance because it demonstrates the application of Chloro Controls to domestic arbitrations and expands the traditional conception of “parties” to an arbitration agreement to include non-signatories based on the facts and circumstances. Based on this decision, it would probably be prudent for parties in a composite transaction involving multiple agreements with arbitration clauses to expressly exclude arbitration in any agreement should that be the intention.

Although Ayyasamy has been subjected to considerable criticism, this decision is important because it clearly reiterates that mere allegations of fraud cannot be used to disable or obstruct a domestic arbitration.

Mere reference in an agreement to another document containing an arbitration clause is insufficient to incorporate the clause


Brief facts: The respondent (Techtrans) was party to a construction agreement that contained an arbitration clause (“any dispute...between the parties…shall be finally settled by binding arbitration”). Under this agreement, the respondent entered into a sub-contract with the appellant (Elite Engineering) that did not contain an arbitration clause. When disputes arose between the appellant and respondent, the appellant filed a petition under section 9 of the Act. This petition was subsequently allowed but the judge left open the issue of existence of an arbitration agreement. Meanwhile, the appellant’s petition under section 11 of the Act to appoint an arbitrator was dismissed by the High Court on the respondent’s contention that there was no arbitration agreement.

Issue: Was the arbitration clause in the construction agreement incorporated into the sub-contract?

Arguments: The appellant argued that (i) the sub-contract incorporates the arbitration agreement in the construction agreement by implication by virtue of the following clauses: clause 2 that provides that “all the conditions and special conditions of contract, specifications (general and additional clauses relating to the works and quality specified in the [construction agreement] are binding on the Subcontractor” [emphasis supplied]; and clause 9.10 of the Annexure that provides that “for items which are not mentioned in this Agreement Clauses, terms and conditions of [the construction agreement] will be applicable” [emphasis supplied].

The result of reading both clauses together was that the arbitration clause in the construction agreement became applicable to the sub-contract by incorporation; (ii) when the appellant was required to execute the work on the terms and conditions contained in the principal agreement (i.e. the construction agreement), the parties clearly intended to incorporate all terms including the arbitration clause; (iii) clause 8.7 of the sub-contract provides that other terms related to termination of work will be same as the agreement between the EPC, Concessionaire and respondent, which would include settlement of disputes on termination through arbitration as provided in the sub-contract; and (iv) the appellant’s statement in its section 9 petition that it would be constrained to file a suit against the respondent was on account of mistaken understanding of law and cannot be held against it.

The respondent argued that clause 2 of the sub-contract clearly demonstrated that there was only a qualified incorporation of the terms and conditions of the construction agreement, namely only those relating to the works and quality. There was no conscious acceptance of the arbitration clause by the parties, which was reflected in the fact that the appellant did not even refer to it in its section 9 petition.

Decision: The Supreme Court agreed with the respondent’s contentions and held that there was no arbitration agreement between the parties. Relying on its verdict in M.R. Engineers and Contractors Private Limited, the Court held that as per section 7(5) of the Act, an arbitration clause in an independent document can be imported into an agreement between parties by reference to such independent document in the agreement, even if there is no specific provision for arbitration. However, what is key is that the reference must be such so as to make the arbitration clause in such independent document a part of the agreement. Therefore there is a difference between mere reference and incorporation, which is made clear by the language of section 7(5):

“Therefore when there is a reference to a document in a contract, the court has to consider whether the reference to the document is with the intention of incorporating the contents of that document in entirety into the contract, or with the intention of adopting or borrowing specific portions of the said document for application to the contract” (paragraph 16; paragraph 16 of M.R. Engineers) [emphasis supplied].

The Court referred to the conditions laid out in M.R. Engineers that need to be fulfilled for a valid incorporation of an arbitration clause and accordingly agreed with the High Court’s conclusion that there was no conscious acceptance of the arbitration clause in the construction agreement by the appellant and respondent. The Court agreed with the respondent that clause 2 had limited coverage, and noted that clause 9.10 only referred to “items” which had to be taken from the principal contracts. Further, the Court rejected the appellant’s termination of work argument, holding that the procedure relating to termination is completely separate and different from resolution of disputes.

Comment: This case is yet another illustration of the requirement to be express and specific in providing for arbitration in an agreement. Parties’ intention to consent to arbitration has to manifest clearly as opposed to appearing as an after thought. As regards the inclusion of arbitration by incorporation, this decision emphasises that the agreement should contain a clear reference to the document/s containing the arbitration clause and the intention to either incorporate the document/s in their entirety or at least the arbitration clause, unlike a reference to mere technical provisions that is likely to prove insufficient.

No comments: