The Ministry of New & Renewable Energy (MNRE) came up with the National Green Hydrogen Mission (NGHM) in January 2023, which aimed: "to provide a comprehensive action plan for establishing a Green Hydrogen ecosystem and catalysing a systemic response to the opportunities and challenges of this sunrise sector." The NGHM recognised India's Net Zero Target of 2070 but also underscored another important but relatively less talked about target: Energy Independence by 2047. The NGHM stated that green hydrogen was seen as playing a critical role in achieving these objectives.
For the uninitiated green hydrogen refers to hydrogen produced by electrolysis using renewable energy. There are other types of hydrogen depending on the emission the process of manufacture gives out. See here, for information on such other types of hydrogen.
Hydrogen Hubs in the NGHM
The NGHM recognises that transportation of hydrogen would be a challenge, both technically and logistically, and therefore provides for cluster production, which would have the following features:
- Large scale production in a given area;
- Utilisation of the produced hydrogen also in the given area;
- Hydrogen hubs will cater to domestic demand as well as to exports
- The hub will have a network of producers, users and supporting infrastructure
- Development of hydrogen infrastructure would have to be done in a coordinated manner and by pooling resources from the Central Govt., State Govt., Local Govt. and the industry
- A hydrogen hub should have a planned/announced capacity of a minimum of 1,00,000 MTPA. Higher production capacity would get more priority under the Scheme.
- Infrastructure, projects and resources would be mapped under the PM Gati Shakti.
- Recognition of hydrogen hubs by MNRE in other places is possible but without financial assistance.
Provisions regarding failure to utilise grants or complete the project would be mentioned in the Call for Proposals.
A Steering Committee (overall monitoring of scheme) and a Project Appraisal Committee (project review) will be constituted. MNRE would nominate Scheme Implementing Agencies (SIAs) to implement the Scheme and hydrogen hubs.