[This guest post penned by Mr. Sameer Sharma, a final year student of the National Law University, Jodhpur, points out and critiques the observations in the recent decision of the Supreme Court of India in Uttarakhand Purv Sainik Kalyan Nigam Limited v. Northern Coal Field Limited (2019:SC) that issues of limitation are jurisdictional issues for the purpose of Section 16 of the Arbitration and Conciliation Act, 1996 although they have been held not to be, as per IFFCO v Bhadra Products (2018:SC).]
The seemingly
inconspicuous observation by the SC in Uttarakhand
Purv on limitation: A potential breeding ground for confusion.
-
Sameer Sharma (5th
year law student at NLU Jodhpur)
In its judgement dated
27.11.2019, the Supreme Court (“SC”) in Uttarakhand
Purv Sainik Kalyan Nigam Limited v. Northern Coal Field Limited,[1] held that the issue of limitation is a "jurisdictional
issue" which would be required to be decided by the arbitral tribunal
under Section 16 of the A&C Act, 1996, and not by the High Court under
Section 11. The purpose of this write-up is to assess the validity and
tenability of this particular observation by the SC, as well as its reliance on
certain cases to reach such conclusion.
For this limited purpose,
it would be adequate to state that the petitioner in the said matter issued a
legal notice dated 29.05.2013 to the respondent seeking payment of dues owed to
it under the contract. On 09.03.2016, almost three years later, the said
petitioner invoked the arbitration clause under the contract by issuing a
notice of arbitration to the respondent. Subsequently, the petitioner
approached the High Court under Section 11 of the Act for the appointment of an
arbitrator. The High Court, vide the order impugned before the SC in the
aforesaid case, refused to appoint an arbitrator stating that the claims of the
petitioner stood barred by limitation.
The SC noted that the invocation of the arbitration clause in the
matter occurred after the 2015 Amendments to the Act came into force. As a
result, the SC considered the insertion of Section 11(6A) in the Act while
dealing with the instant case before it. By relying on its earlier judgement in
Duro Felguera S.A. v. Gangavaram Port Limited,[2]
the SC in Uttarakhand Purv held
as follows: -
“9.8. In view of the
legislative mandate contained in Section 11(6A), the Court is now required only
to examine the existence of the arbitration agreement. All other preliminary or threshold issues are left to be decided by
the arbitrator under Section 16, which enshrines the Kompetenz-Kompetenz principle.”
(emphasis
supplied)
After
observing the same, the SC went on to hold: -
“9.11. Sub-section
(1) of Section 16 provides that the arbitral tribunal may rule on its own
jurisdiction, “including any objections” with respect to the existence or
validity of the arbitration agreement. Section
16 is as an inclusive provision, which would comprehend all preliminary issues
touching upon the jurisdiction of the arbitral tribunal. The issue of
limitation is a jurisdictional issue, which would be required to be decided by
the arbitrator under Section 16, and not the High Court at the pre-reference
stage under Section 11 of the Act. Once the existence of the arbitration
agreement is not disputed, all issues, including jurisdictional objections are
to be decided by the arbitrator.”
(emphasis
supplied)
“9.12. In Indian
Farmers Fertilizers Cooperative Ltd. v. Bhadra
Products, this Court
held that the issue of limitation
being a jurisdictional issue, the same has to be decided by the tribunal under
Section 16, which is based on Article 16 of the UNCITRAL Model Law
which enshrines the Kompetenze principle.”
(emphasis
supplied)
Right at
the outset, it would not be incorrect to state that the reasoning employed by
the SC in the instant case relating to the issue of limitation, is ridden with anomalies.
There are two broad reasons for this contention. Firstly, it is contrary to the
SC’s earlier decision in IFFCO (which
was, akin to Uttarakhand Purv, a
judgement rendered by two judges). In IFFCO,
the SC definitively and categorically held that an issue of limitation
dealt with by an arbitral tribunal does not fall under Section 16 of
the Act; rather, such decision by the tribunal would amount to an “interim award”
(which can only be subject to challenge under Section 34 of the Act).[6]
In fact, the SC in Uttarakhand Purv
has quoted and relied on IFFCO (as
can be seen from the extracted paragraph no. 9.12 reproduced above) to state
the exact opposite of what has actually been held in it!
Secondly,
the SC’s reliance on ITW Signode and NTPC v. Siemens is also misplaced. The SC in IFFCO clearly makes the effort to address the reliance placed by
the party therein on ITW Signode to
state as to how such judgement does not apply to the facts contained in that
matter therein. The SC elaborately distinguishes ITW Signode in IFFCO.[7]
However, despite such exposition, the SC in Uttarakhand Purv rather carelessly resorts to ITW Signode to fortify its reasoning. Insofar as NTPC v. Siemens is concerned, nowhere does the SC state in the said case
that a decision on the issue of limitation would come under Section 16 of the
Act (as has been suggested by the SC in Uttarakhand
Purv). Again, this point has also squarely been addressed by the SC in IFFCO.[8]
In light
of the foregoing analysis, it is the view of the author that the SC’s holding
in Uttarakhand Purv suffers from
infirmities as it is manifestly contrary to established case-law and as it
misinterprets precedents laid down by the SC. It must be borne in mind that the
SC in Uttarakhand Purv was dealing
with a Section 11-scenario (appointment of arbitrators) and with the question
as to whether it is the Court u/S 11 or the arbitral tribunal u/S 16 of the Act
which must adjudicate on an issue related to limitation. However, while the
SC’s conclusion that the Court u/S 11 must not deal with the issue of
limitation as it must confine itself to deciding the “existence of arbitration
agreement” is statutorily sound, the dictum that such issue of limitation must
be dealt with under Section 16 is per
incuriam. In other words, while the end sought to be achieved is valid, the
means employed to achieve such end is what is problematic. It is per incuriam because it explicitly
refers to judgements to ultimately end up stating the opposite of what the case
referred to actually holds.
It seems
to be the case that the SC has employed an all-or-nothing approach to the
extent wherein it has held that “all
preliminary or threshold issues” have to be dealt with only u/S 16 of the
Act and not u/S 11 of the Act. The SC has not contemplated a situation in which
certain issues can be outside the ambit of determination u/S 11 and yet be
beyond the (limited) realm of Section 16 of the Act. This eventuality, as has
been discussed in the foregoing analysis, is very well plausible, with the
prime example being the ratio in IFFCO. Thus, the SC could have, in the
author’s respectful submission, stated that while the issue of limitation
cannot be gone into by the Court u/S 11 of the Act, it could most certainly be
dealt with by the arbitral tribunal in the usual course as per relevant
provisions of the Act. This would have prevented the conflict of opinion with IFFCO. The
need for judicial discipline, adherence to precedents and legal certainty would
necessitate courts to render as few conflicting decisions as possible,
especially when it comes to co-ordinate bench judgements. A scenario, for
instance, like the one relating to the interpretation of the amended Section 6
of the Hindu Succession Act, 1956, which today involves the need to harmonise
conflicting decisions,[9]
must be avoided.
With the
decision in Uttarakhand Purv, the
already settled issue on whether a decision on limitation constitutes an
“award” or an “order” (u/S 16 of the Act) has now been thrown open to
re-interpretation and disputation. One can expect this to be a ripe ground for
future litigation and resultant uncertainty.
[1] Uttarakhand Purv Sainik Kalyan Nigam Limited v.
Northern Coal Field Limited, MANU/SC/1634/2019, para 9.11 (hereinafter “Uttarakhand Purv”).
[2] Duro Felguera S.A. v. Gangavaram Port
Limited, (2017) 9 SCC 729.
[3] ITW Signode India Limited v Collector of Central Excise, (2004) 3
SCC 48 (hereinafter “ITW Signode”).
[9] Vineeta Sharma v. Rakesh Sharma, MANU/SC/1593/2018.
2 comments:
Good Analysis.
informative
Post a Comment