-Mr. HM Seervai, Preface to the 1st ed., Constitutional Law of India.
Monday, September 21, 2026
Non-Recoverable Contract Costs in Bangladesh’s Model PSC 2026
Thursday, September 17, 2026
Costs Not Recoverable under the Sri Lankan Model Petroleum Resources Agreement
Sri Lanka's Model Petroleum Resources Agreement (2026) (SLMPRA) is one of the recent Production Sharing Contracts (PSC) published and available. Link to the SLMPRA is provided at the end of this post. For a PSC, the length of the SLMPRA is only 95 pages. Cost recovery is one of the important provisions of a PSC. Costs allowed to be recovered and costs not allowed to be recovered form some of the crucial provisions of a PSC. This post discusses the cost items which are not recoverable.
Article 21 of the SLMPRA deals with Recovery of Cost Petroleum. Article 1 defines "Agreement Costs" as "Exploration Costs, Development Costs and Production Costs as provided for in the PRA and which are deemed to be recoverable costs in terms of Article 21 of the PRA;". Article 21.2 classifies these costs into "Production Costs", "Exploration Costs" and "Development Costs" incurred by the Contractor.Article 21.12 pertains to costs not recoverable. It contains a whopping list of 31 items! If these costs can be classified into distinct buckets, such a classification would be as follows:
|
Category |
Description |
Clause / Item Numbers |
|
Before SLMPRA or outside Area/ Outside Sri Lanka |
Costs before Effective Date, costs related to administrative overhead
outside of Sri Lanka for specific items; Income/ other tax incurred outside
Sri Lanka; Costs outside measurement point |
1, 4, 9, 10, 19 |
|
Specific Payments/ Costs/ obligations under MPRA |
Expenditure incurred in obtaining, furnishing and maintaining the
guarantees, expenses of the members of the Advisory Committees and other
Committee, Environment studies protection, Abandonment fund, Training costs. Production
bonus, Signature bonus, royalty, |
17, 25 to 31 |
|
Excess costs/ gold plating/ negligence/ misconduct/ |
costs of goods and services in excess of the international market price
for goods or services; charges for goods and services not in accordance with
the relevant agreement with sub-contractor or supplier; Charges for goods in
excess of the amount allowed by Article 21.12; Costs not reasonably required
for petroleum operations; costs of materials and services in excess of the
values established under the principles in Article 21.12; costs and
expenditure as result of wilful misconduct or negligence of Contractor; |
5, 6, 7, 8, 20, 24 |
|
Unsupported/ Unapproved Costs |
costs for which original records do not exist or are not correct in
any material respect; any costs not included in approved work program and
budget, unless resulting from an emergency; Emergency expenditure incurred but
not reported within time |
3, 14, 16, |
|
Fines/ penalties |
fines and penalties imposed by any Authority |
12 |
|
Non-fulfilment of contractual obligations with third parties |
amounts paid with respect to non-fulfilment of a contractual
obligation to a third party; Indemnities spent on Non-fulfilment of
contractual obligations with third parties |
17, 22 |
|
Unrelated to
petroleum operations |
Expenditures
for securing funds for petroleum operations; donations, contributions, or
public expenditure; costs involved in creation and management of any
partnership/ joint venture arrangement, or costs of acquisition of an
interest under the Agreement |
2, 13,21 |
|
Dispute
resolution |
Costs of
expert determination of arbitration; attorney’s fee and other costs related
thereto. |
11, 18 |
|
Others |
costs
incurred which are covered by insurance for Included Risks, are a result of
failure to insure where insurance is required pursuant to the Contract, etc. |
23 |
The items not cost recoverable have been classified into nine distinct buckets. This PSC has one of the longest list of items that are not cost recoverable. Like in any other PSC, there are bound to be disputes on individual items in this long list.
It would be interesting to see if the recent Model PSCs disclose such a trend, given their experience and experience of other countries in dealing with cost recovery related issues.
Sri Lanka MPRA (2026) can be downloaded from here.
Saturday, January 3, 2015
PSC Awards: Great Eastern Energy Corporation v MoPNG
Great Eastern Energy Corporation Ltd. v. MoPNG
Sunday, July 20, 2014
PSC Awards: Selan Exploration v MoPNG
Friday, April 4, 2014
SC Withdraws Appointment of Foreign Arbitrator in D6 Cost Recovery Arbitration
Tuesday, April 1, 2014
D6 Cost Recovery Arbitration: SC appoints Foreign Arbitrator
- Right of the Operator to invoke arbitrator on behalf of the Consortium in the Production Sharing Contracts.
- Appointment of foreign national as arbitrator in International Commercial Arbitration.
- Power of a party nominated arbitrator to tender legal advice
Thursday, December 20, 2012
Relationship between Operator and the Non-Operators in Petroleum Operations
- Geological risks- risk of not finding any petroleum in commercially viable quantities
- Financial risks- risk that exploitation of the commercially viable quantities of petroleum is far complicated and therefore costlier than initially estimated or change in the economic laws of the host nation drastically increasing the costs to be expended
- Political risks- instability in the region such as civil war, riots, etc thereby resulting in loss of investments.
- the JOA authorizes the Operator to award contracts without the approval of the Operating Committee,
- the JOA authorizes the Operator to award only contracts below a specific value without the approval of the Operating Committee, and
- the JOA requires all contracts to be approved by the Operating Committee. In such cases, the Operator is bound to follow relevant procedure, as applicable. If no consent is taken when the JOA makes it mandatory, the Non-Operators would be entitled to refuse to share the costs and risks for such contracts.
Tuesday, July 19, 2011
Bombay High Court Decides the Natural Gas Allocation Dispute
- The Petitioners (Welspun Maxsteel & Ispat Industries) contend that once the MOPNG made firm allocation of natural gas and asked the Petitioners to enter into Gas Sale and Purchase Agreements (GSPA) with the Contractor (RIL & Niko), curtailment in the supply of natural gas cannot be done. As has been held by the Supreme Court in the case of RNRL v. RIL, ownership of natural gas is vested with the Union of India (UoI), which holds the scarce natural resources in public trust. In the same case, the Gas Utilization Policy of the UoI has been held to be in conformity with the Constitution. Significantly, the decision holds that the UoI has the power "regulate and distribute the manner of sale of natural gas through allotments and allocation which would subserve the best interests of the country." The judgement also states unequivocally that the Production Sharing Contract would "override any other contractual obligation between the contractor and any other party”, including the Gas Sale and Purchase Agreement (GSPA).
- The Petitioners argue that the EGOM's (Empowered Group of Ministers) Policy has been entirely overhauled by the MOPNG. A perusal of the decisions of the EGOM shows that the EGOM had accorded high priority to certain sectors such as fertilizer etc (Core Sectors). Also, as per the decisions of the EGOM, firm allocation to steel plants such as those of the Petitioners would be only after demand from the core sectors were met. Therefore, there is no basis in the Petitioners' contention. Similarly, the contentions of the Petitioners that the MOPNG does not have any power to curtail the supply if the daily production is above 40 mmscmd must fail. In fact, all EGOM decisions empower the MOPNG "to take decisions regarding the supply of natural gas to sectors/individual customers consequent to gas being available on account of short offtake, delay and any other unforeseen circumstances." (Emphasis in the original) The EGOM has laid down the broader policy regarding the determination of core and non-core sectors, the overall principles regarding supply allocation and distribution and has empowered the concerned Ministry, the MOPNG, to implement its decisions in public interest.
- The Petitioners rely on the doctrine of promissory estoppel. According to them, since the EGOM decided on the allocation to the steel industry and when firm allocations were made to the petitioners, the government cannot curtail the supply of natural gas in view of the doctrine of promissory estoppel. The Petitioners contention cannot be upheld. Natural gas is a scarce resource and the decision taken by the MOPNG was in public interest. It has been recognised in several decisions of the Supreme Court, including in Shrijee Sales vs Union of India, Kasinka Traders vs Union of India, M. P. Mathur Vs. DTC and State of West Bengal Vs. Niranjan Singha, that there can be no promissory estoppel against public interest
- In proceedings pertaining to judicial review of administrative action, courts do not review the merits of the decision but merely review the decision making process. The Petitioners have, in effect, asked to court to sit on appeal over the decision of the MOPNG, which is not possible.
Thursday, June 23, 2011
Gas Dispute, Cairn's Revenge, the Production Sharing Contract: Updates
- Gas allocation to the fertilizer sector should be prioritized due to the Kharif Season.
- The power sector needs priority because of the extreme summer conditions.
- This action by the Government would lead to savings in subsidy to the tune of Rs. 1251 crores to the government
Wednesday, May 11, 2011
Gas Allocation & Utilization in India: Further Developments
Tuesday, May 10, 2011
Natural Gas Allocation and Utilisation in India: Matter Goes to Court
| Reliance D 6* |
About 3.2 mmscmd gas was supplied from D6 to Essar Steel. However, of late, D6 field has not been producing enough natural gas, leading to strict directions from the Exploration & Production regulator-Directorate General of Hydrocarbons to RIL. This Direction is a possible consequence of the low production. Essar Steel challenged the Direction to RIL. Essar Steel had also asked for an interim stay on the direction of the MOPNG. However, the Delhi High Court refused to grant stay without hearing the Government. When the court asked for the contentions of the Government with the Additional Solicitor General, Mr A.S. Chandiok (ASG), the ASG asked for more time to review the decision of the Bombay High Court on a similar matter that arose out of petitions filed by Welspun Maxsteel and a few others.
Proceedings before the Bombay High Court:
The Direction was also the subject matter of a petition filed in the Bombay High Court by Welspun Maxsteel. Relevant portions of the impugned Direction dated April 21, 2011 reads as follows:
“2. Under the Government's Gas Utilization Policy, allocations for KG D6 fields had initially been made for core sectors and subsequently, taking into account expectation of higher production, allocations had been made for non-core sectors. As the gas production from KG D6 fields has decreased to around 50 mmscmd, it is only natural that the said production be supplied firstly to core sectors and Ministry's direction vide letter of even number dated 30.03.2011 has been issued in this context. The said direction has been issued in pursuance of Government's Gas Utilization Policy under the provisions of the PSC. Hence, the said direction needs to be complied with.It may be noted that he MOPNG has been deciding on the allocation of natural gas to different sectors for a long time. As regards natural gas from the D6 Field, Government had, though an EGoM (Empowered Group of Ministers), framed a policy, known as Gas Utilisation Policy (June 2008), for the allocation of gas to various sectors. The said policy also contained certain general directions for the allocation of natural gas in respect of all NELP (New Exploration Licence Policy) Production Sharing Contracts. Following are the features of the general guidelines:
3. The Hon'ble Supreme Court in its order dated 7.5.2010 in the RIL & RNRL case has held that the Government owns the gas till it reaches its ultimate consumer. Further, it has been held that the PSC shall override any other contractual obligation between the Contractor and any other party.”
- The marketing priorities for the sale of gas from NELP Blocks would be determined by the Government and the sale would be on the basis of pricing formula approved by it.
- Gas allocation to a particular sector would not mean reservation or quota to that particular sector. In case consumers of a particular priority sector are not in a position to take gas when available, the gas not taken would be first offered to other entities in that priority sector and if they are not in a position to take the gas, the gas not taken would go to the sector which is next in priority.
- The priority for gas supply would be applicable only to customers who are connected to the existing pipelines network. In the absence of a network, a small or marginal field could sell the gas to customers connected to or can be connected to (within a short period of three- six months) it.
- This prioritization would not affect the process of price discovery as all customers would participate in the price discovery process (as per the extant policy of the EGoM) and would be eligible for utilizing natural gas subject to priority.
- This guidelines would be reviewed after five years
- Gas based urea plants
- Gas based LPG plants
- Liquid Fuel plants and power plants lying idle or underutilized
- City Gas distribution
- Gas based power plants
"21.1 Until such time as the total availability of Natural Gas from all Petroleum production activities in India meets the total national demand as determined by the Government, each Company comprising the Contractor, shall sell in the domestic market in India all of the Company’s entitlement to Natural Gas from the Contract Area.
21.3 For the purpose of domestic sale obligation, the Contractor shall have freedom to market the Natural Gas and sell its entitlement as per Government Policy for utilization of gas among different sectors.The second source comes from the Constitution itself. Article 73 read with Entry 53, List I of Schedule VII. Entry 53 reads:
21.3.1 For purposes of Article 21, the Government may from time to time frame policy for utilization of gas among different sectors, both for Associated Natural Gas (ANG) as well as Non-Associated Natural Gas (NANG) which would cover issues relating to gas supplies to different consumer sectors."
"Regulation and development of oilfields and mineral oil resources; petroleum and petroleum products; other liquids and substances declared by Parliament by law to be dangerously inflammable."Now, in the Welspun Maxsteel case, it was argued that if no gas was supplied to the petitioners, their manufacturing process would come to a standstill and this would have a cascading effect on the economy. A two judge Bench consisting of Ranjana Desai & Ranjit More, JJ. were of the opinion that the Union of India has to hold a meeting with the petitioners to sort out their grievance. The Bench ordered the matter to be heard on May, 9, 2011. The order can be accessed from here. On May 9, the Vacation Bench consisting of Mridula Bhatkar & RG Ketkar, JJ heard the matter.In the said hearing, the counsel for Union of India stated that a meeting would be conducted on May 11 between the petitioners, representatives of other non-priority sectors affected by the decision of the Government, and the MOPNG and a decision on the matter would be communicated to the petitioners by May 19, 2011. The court adjourned the matter to May 23, 2011. The order can be downloaded from here.
It would be interesting to see what the MoPNG would do. We will keep our readers updated.
* Image from here.