"I realise that some of my criticisms may be mistaken; but to refuse to criticize judgements for fear of being mistaken is to abandon criticism altogether... If any of my criticisms are found to be correct, the cause is served; and if any are found to be incorrect the very process of finding out my mistakes must lead to the discovery of the right reasons, or better reasons than I have been able to give, and the cause is served just as well."

-Mr. HM Seervai, Preface to the 1st ed., Constitutional Law of India.
Showing posts with label Production Sharing Contracts. Show all posts
Showing posts with label Production Sharing Contracts. Show all posts

Monday, September 21, 2026

Non-Recoverable Contract Costs in Bangladesh’s Model PSC 2026


In last week’s post, we discussed various non-recoverable costs in the recent Sri Lankan Model Petroleum Resources Agreement. In this post, we discuss non-recoverable costs Bangladesh’s recent Model Offshore Production Sharing Contract (“PSC”).



Clause 14.3 of the Model PSC states:

“Subject to the Accounting Procedure and the auditing provisions of this Contract, Contractor shall recover all costs and expenses not excluded by the provisions of this Contract and the Accounting Procedure in respect of all the Exploration, Appraisal, Development, Production, Abandonment and related operations hereunder with respect to the Contract Area to the extent of and out of a maximum of seventy five percent(75%) of Petroleum from both shallow and deep sea blocks per Calendar Year of all Available Oil/ Natural Gas/ Condensate/ NGL from the Contract Area (hereinafter referred to as "Cost Recovery Petroleum").” (emphasis added)

Clause 14.3 excludes recovery of those costs which are held as such in the PSC and its Accounting Procedure (Annexure-B to the Model PSC). Section 7 of the Accounting Procedure contains a list of 26 heads of non-recoverable costs.

Similar to the exercise we did for Sri Lanka’s MPRA, we have classified these 26 heads into distinct buckets and have tabulated it:

Category

Description

Section 7 Items

Before Effective Date / Outside Bangladesh / Outside Measurement Point

Costs incurred before the Effective Date not incurred under Work Program and Budget; costs incurred beyond the measurement point; income tax and other taxes incurred outside Bangladesh; certain administrative overhead outside Bangladesh.

c, h, i, s

Financing and Fund-Raising Costs

Interest and financing charges; expenditure to negotiate, obtain or secure funds, exchange losses on financing, etc.; expenditure for furnishing and maintaining bank guarantees and indemnities

a, q, r

Unsupported / Unapproved Costs

Costs lacking proper original records; charges for goods & services unsupported by supplier/ sub-contractor agreement costs; not included in approved Work Program and Budget; emergency expenditure not timely reported to Petrobangla; donations and contributions not pre-approved by Petrobangla; benefits not identified as recoverable under Section 3.1(c).  

b, e, m, n, p, v

Excess Costs / Gold-Plating / Unreasonable Expenditure

Goods and services priced above international market rates; material costs exceeding permitted values; costs not reasonably required for Petroleum Operations; materials and services exceeding allowable valuation principles.

d, f, g, t

Taxes and Contractual Payments

Income tax payable by Contractor; payments under Articles 20.1-20.4 (bonuses) and 25.6 (training of Petrobangla employees).

j, o

Dispute Resolution Costs

Costs of expert determination and arbitration.

k

Fines, Penalties; losses from PSC and third party contracts; negligence

Fines and penalties; Costs resulting from willful misconduct or negligence of Contractor; amounts paid with respect to non-fulfillment of a contractual obligation with third party and loss due to non-compliance of PSC

l, x, z

Partnership / Joint Venture / Acquisition Costs

Costs of creating or managing partnerships or joint ventures; acquiring interests in the Contract or Contract Area.

u

Insurance-Related Exclusions

Costs covered by insurance; losses resulting from failure to insure; recoverable insured losses not claimed; losses that would have been covered under approved self-insurance arrangements.

w(i)-(iv)

Committee and Governance Costs

Expenses of members of the Joint Management Committee (JMC) and Joint Review Committee (JRC).

y


Like the Sri Lankan MPRA, Bangladesh's Model PSC also displays a long list of items that are not cost recoverable.

Thursday, September 17, 2026

Costs Not Recoverable under the Sri Lankan Model Petroleum Resources Agreement

 Sri Lanka's Model Petroleum Resources Agreement (2026) (SLMPRA) is one of the recent Production Sharing Contracts (PSC) published and available. Link to the SLMPRA is provided at the end of this post. For a PSC, the length of the SLMPRA is only 95 pages. Cost recovery is one of the important provisions of a PSC. Costs allowed to be recovered and costs not allowed to be recovered form some of the crucial provisions of a PSC. This post discusses the cost items which are not recoverable.

Article 21 of the SLMPRA deals with Recovery of Cost Petroleum. Article 1 defines "Agreement Costs" as "Exploration Costs, Development Costs and Production Costs as provided for in the PRA and which are deemed to be recoverable costs in terms of Article 21 of the PRA;". Article 21.2 classifies these costs into "Production Costs", "Exploration Costs" and "Development Costs" incurred by the Contractor.

Article 21.12 pertains to costs not recoverable. It contains a whopping list of 31 items! If these costs can be classified into distinct buckets, such a classification would be as follows:

Category

Description

Clause / Item Numbers

Before SLMPRA or outside Area/ Outside Sri Lanka

Costs before Effective Date, costs related to administrative overhead outside of Sri Lanka for specific items; Income/ other tax incurred outside Sri Lanka; Costs outside measurement point

1, 4, 9, 10, 19

Specific Payments/ Costs/ obligations under MPRA

Expenditure incurred in obtaining, furnishing and maintaining the guarantees, expenses of the members of the Advisory Committees and other Committee, Environment studies protection, Abandonment fund, Training costs. Production bonus, Signature bonus, royalty,

17, 25 to 31

Excess costs/ gold plating/ negligence/ misconduct/

costs of goods and services in excess of the international market price for goods or services; charges for goods and services not in accordance with the relevant agreement with sub-contractor or supplier; Charges for goods in excess of the amount allowed by Article 21.12; Costs not reasonably required for petroleum operations; costs of materials and services in excess of the values established under the principles in Article 21.12; costs and expenditure as result of wilful misconduct or negligence of Contractor;

5, 6, 7, 8, 20, 24

Unsupported/ Unapproved Costs

costs for which original records do not exist or are not correct in any material respect; any costs not included in approved work program and budget, unless resulting from an emergency; Emergency expenditure incurred but not reported within time

3, 14, 16,

Fines/ penalties

fines and penalties imposed by any Authority

12

Non-fulfilment of contractual obligations with third parties

amounts paid with respect to non-fulfilment of a contractual obligation to a third party; Indemnities spent on Non-fulfilment of contractual obligations with third parties

17, 22

Unrelated to petroleum operations

Expenditures for securing funds for petroleum operations; donations, contributions, or public expenditure; costs involved in creation and management of any partnership/ joint venture arrangement, or costs of acquisition of an interest under the Agreement

2, 13,21

Dispute resolution

Costs of expert determination of arbitration; attorney’s fee and other costs related thereto.

11, 18

Others

costs incurred which are covered by insurance for Included Risks, are a result of failure to insure where insurance is required pursuant to the Contract, etc.

23

The items not cost recoverable have been classified into nine distinct buckets. This PSC has one of the longest list of items that are not cost recoverable. Like in any other PSC, there are bound to be disputes on individual items in this long list. 

It would be interesting to see if the recent Model PSCs disclose such a trend, given their experience and experience of other countries in dealing with cost recovery related issues. 

Sri Lanka MPRA (2026) can be downloaded from here.

Saturday, January 3, 2015

PSC Awards: Great Eastern Energy Corporation v MoPNG

In July this year, we made public an arbitral award in the arbitration between Selan Exploration and the Ministry of Petroleum and Natural Gas (MoPNG). We had assured our readers that we would be bring a few such arbitral awards to the public domain considering their precedential and academic value.

In this second post in the series, we bring to the public domain the arbitral award in the disputeb between Great Eastern Energy Corporation Ltd. (Great Eastern) and the MoPNG. The central issue in the dispute was the quantum of signature bonus to be provided by Great Eastern to the MoPNG. The three member arbitral tribunal upheld the stance of the MoPNG and directed Great Eastern to pay the amount claimed with interest. The arbitral award can be accessed from the below link:

Great Eastern Energy Corporation Ltd. v. MoPNG

Sunday, July 20, 2014

PSC Awards: Selan Exploration v MoPNG

We bring to readers certain arbitral awards which have been rendered under the Production Sharing Contracts between the Ministry of Petroleum and Natural Gas and the Contractor(s). The purpose of doing so is to bring these awards to the public domain as it throw light on how Production Sharing Contracts are interpreted. It is expected that these awards would be useful to litigants as well as academicians.

The first of this series is the award pursuant to arbitration between Selan Exploration v. Ministry of Petroleum and Natural Gas. The dispute pertained to share of profit petroleum between the Contractor and the Government. The case also deals with the calculation of the Investment Multiple which forms an integral part of the Production Sharing Contract. The award can be accessed from here.

Friday, April 4, 2014

SC Withdraws Appointment of Foreign Arbitrator in D6 Cost Recovery Arbitration

In a recent post, we had commented on the judgement of the Supreme Court on Monday (31.03.2014) appointing a foreign arbitrator (Justice Spigelman, Australia) as the third and presiding arbitrator in the arbitration proceedings under the Production Sharing Contract between RIL Consortium (consisting of Reliance Industries Ltd., British Petroleum and Niko Resources) and the Ministry of Petroleum and Natural Gas, Government of India. The matter was once again mentioned in the Supreme Court on Wednesday (02.04.2014) by the counsel for the Government of India wherein it was contended that the arbitrator appointed by the Supreme Court was in fact the first in the list of arbitrators submitted by RIL Consortium. The counsel for RIL Consortium agreed and therefore the judge had no other option but to withdraw the order of appointment. 

The appointment became a controversy because the judge had in his judgement stated that he had conducted an independent "survey" in finding a suitable arbitrator. In the withdrawal order, the judge stated that a "substitute arbitrator shall be appointed subsequently by a separate order." The withdrawal order can be accessed from here. News reports on the withdrawal can be accessed from here and here. 

Tuesday, April 1, 2014

D6 Cost Recovery Arbitration: SC appoints Foreign Arbitrator

The Supreme Court's decision yesterday nominating a foreign national as arbitrator in the dispute between the Reliance-BP-Niko Consortium (RIL Consortium) and the Ministry of Petroleum and Natural Gas (UoI) regarding cost recovery in the D6 Block has been reported by several news papers (see here and here, for example). But for a few aspects, the case does not necessitate a lengthy and complicated legal analysis. Hence, these noteworthy aspects are discussed in this post apart from a brief description of the case.

Brief Facts: 

UoI entered into a Production Sharing Contract (PSC) for petroleum exploration and production with Reliance Industries Limited (Reliance) and Niko Resources. Subsequently, British Petroleum also became a member of the RIL Consortium. Disputes arose between UoI and RIL Consortium regarding the right of UoI to restrict recovery of costs incurred by the consortium from the petroleum production in the block owing to fall in production levels. In November 2011, Reliance invoked arbitration under the PSC and nominated Justice SP Bharucha as the arbitrator. Initially, UoI stated that arbitration was prematurely invoked as there was no dispute between the parties. Reliance disagreed in view of the "long standing controversy" between the parties. Correspondences ensued. Subsequently, in April 2012 Reliance and Niko filed a petition in the Supreme Court for appointment of arbitrator by UoI. During the pendency, Justice VN Khare was appointed as arbitrator by UoI. Hence, the petition was disposed of. Since both parties had no objection to the arbitrator appointed by the other side, the court ordered that the arbitration clause pertaining to appointment of the third arbitrator may be followed. However, both the arbitrators failed to agree on the third arbitrator for almost a year since the order of the Supreme Court. Therefore, Reliance filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 (1996 Act) for appointment of the third arbitrator. 



Decision: 

Justice SS Nijjar who heard the matter "discretely conducted a survey to find a suitable third arbitrator who is not a National of any of the parties involved in the dispute" and appointed Justice James Spigelman, former Chief Justice & Lieutenant Governor of New South Wales, Australia as the third arbitrator and Chairman of the arbitral tribunal.

Comments:

The decision to appoint the third arbitrator is straightforward and not controversial, especially since the issue was to whether there was a dispute between the parties was resolved in the previoust arbitration petition. However, the following aspects merit discussion: 
  • Right of the Operator to invoke arbitrator on behalf of the Consortium in the Production Sharing Contracts. 
  • Appointment of foreign national as arbitrator in International Commercial Arbitration. 
  • Power of a party nominated arbitrator to tender legal advice 
Right of the Operator to invoke Arbitration:

The Operator is a party of the Consortium which forms the Contractor in Production Sharing Contracts. The Operator acts on behalf of the Consortium in the day-to-day operations of the work under the PSC. The Operator is generally nominated owing to its participating interests (stake) in the Contractor or due to its expertise. Often, the Operator invokes legal action, including arbitration, either against the UoI or against a Contractor. The question that often arises is whether the Operator can do so even on behalf of the parties when there is no express authorisation from the other parties to do so. For instance, in this case, all the correspondences, including the notice invoking arbitration were addressed by RIL without even mentioning that RIL was acting on behalf of the Consortium. Further RIL and Niko had petitioned the Supreme Court for appointment of UoI's arbitrator when by that time the Government had approved assignment of 30% participating interests of RIL to British Petroleum. Another issue was that Niko and BP did not even dispute the inadmissibility of cost recovery by the UoI. These aspects were pointed out by UoI but opposed by the RIL Consortium. However, Justice SS Nijjar disagreed with these for the following reasons:





"52. It is also not possible to accept the submission of Mr. Anil Divan that Niko and BP are not operators under the PSC and, therefore, have forfeited any right to operations under the PSC. It is also not possible to accept the submission that Niko and BP are not the parties to the dispute with the Respondent. I am of the considered opinion that the provisions of the PSC clearly identified the parties to the PSC. The disputes that have arisen between the parties are also clearly identified in the correspondence exchanged between the parties. The three named contractors are, in fact, frequently mentioned in the correspondence between the parties. It has been correctly highlighted by Mr. Salve that the terms of the PSC have to be considered in the light of the fact that the Respondent expressly consented, after detailed inquiry, to the assignment of participation interests in the PSC to BP. It is a matter of record that Niko has been a party to the PSC from the beginning. Therefore, at-least at this stage, it would not be possible to accept the submission of Mr. Divan that BP and Niko are not "operating” under the PSC."

While the conclusion reached by the Court was correct, the reasonings do not reflect a correct understanding of the PSC. Following are the reasons: 

Under the PSC, a party is nominated as the Operator by the Contractor. Even in this case, RIL was the Operator (Para 5 of the Judgement). When so, how could it be said that Niko and BP were also operators (See the first and the last lines of the above quote). 

Merely because UoI consented to the assignment of participating interests by Reliance to BP does not make it a party to the arbitration. It is possible that one party constituting the Contractor might have a dispute while the other Contractor parties may not be a party to such dispute (Eg. Canoro Resources v. Union of India). For instance, UoI may terminate the PSC vis-a-vis a Contractor party for non-compliance of the PSC obligation to seek approval prior to assignment of participating interests. In such a case, such party alone may invoke arbitration against termination. 

Merely because BP and Niko were mentioned in several correspondences between RIL and UoI would not make them parties to the arbitration. 

The question as to whether BP and Niko had invoked arbitration or not is a question which should have been decided by the court under Section 11. Unless arbitration was invoked, there is no question of exercise of power under Section 11. This question clearly comes within the scope of "the existence of the condition for the exercise of his power" as provided in Para 46(iv) of the judgement in SBP & Co. v. Patel Engineering. 

The eventual decision that BP and Niko were parties to the dispute is correct. Under the Joint Operating Agreement (JOA) between the members of the RIL Consortium, of which UoI had notice (para 6), the scope and authority of the Operator would be provided. In the said JOA, the Operator would be authorised by the consortium members to act on behalf of the parties. The JOA generally specifies those issues for which prior approval is required from the parties and those issues for which the Operator is merely obligated to inform the members. Hence, the Operator would have had the authority to invoke arbitration. Secondly, the issue of disallowance of cost recovery impacts not only the Operator but also all the parties to the Consortium. This being the situation, unless there was an express stance that BP and Niko disagreed with Reliance's stance, it could be presumed that they agreed with the stance of Reliance and authorised Reliance to proceed. Thirdly, in the Petition filed for appointment of the second arbitrator, Niko was also a party. Conseuqently, it cannot be contended that Niko did not agree with Reliance's stance (It is however, not clear why BP did not join the petition, especially when the PSC was also amended much prior to the filing of the said petition.). UoI wrote a letter in May 2012 addressed to all the parties forming the Contractor in the PSC and not just Reliance alone contending that the Contractor had breached the PSC (para 15 of the judgement). Further, Para 14 of the judgement of the SC clearly recognises that the "Petitioners", that is, RIL Consortium had denied vide letter written to UoI in June 2012 the contentions of UoI that they had breached the PSC. In reply, UoI wrote in July 2012 calling upon the petitioners, Niko and Reliance to withdraw the arbitration petition filed for appointment of UoI's arbitrator. These circumstances clearly point out that Niko and BP were also disputing parties in the arbitration. 

Appointment of foreign national as arbitrator in International Commercial Arbitration:

The Supreme Court deviated from its practice of disregarding the spirit of Section 11(9), which provides that in case of International Commercial Arbitration the court "may appoint an arbitrator of nationality other than the nationalities of the parties where the parties belong to different nationalities." and appointed a foreign arbitrator. Section 11(9) recognises the concept of neutrality in international arbitration. However, the Supreme Court has disregarded the same in the past and had appointed retired Supreme Court judges as arbitrator. 


This was not always the position of the court. The Supreme Court considered the word "may" in Section 11(9) to mean "shall" in Dolphin International Ltd. v. Ronak Enterprises Inc. 1998(2) Arb LR 313 (SC)and appointed a person of neutral nationality. While doing so, the judge noted that when the matter was previously listed before Justice Punchhi, he had orally observed that "may" in that section should read as "shall". This was the basis for the court to come to such a conclusion. In Malaysian Airlines Systems Bhd (II) vs. M/s. STIC Travels (P) Ltd. AIR 2001 SC 358, the Supreme Court held that Section 11(9) was not analysed in detail in Dolphin International and that if the foreign party did not object to the appointment of a non-neutral party, there was no reason why an Indian arbitrator should be appointed. It was further held that nationality of the parties should be one of the factors while deciding the arbitration but not the sole factor. 

In Grid Corporation of Orissa Ltd. v. AES Corporation (2002) 7 SCC 736, the question was whether the decision of the two party appointed arbitrators to appoint the a neutral third arbitrator was under the mistake of Indian law. The Supreme Court took note of the Malaysian Airlines decision wherein it was held that "may" in Section 11(9) is not "shall" but importantly, the court went on to hold that "there is nothing wrong in the two arbitrators having formed an opinion inconsultation with each other that a person of third nationality would bepreferable as presiding arbitrator." Thus, till 2002, the prevailing view on Section 11(9) was that in appointing the third (or the sole arbitrator) nationality of the parties is a relevant consideration; the exception being that where the foreign party did not object to the appointment of an Indian arbitrator an Indian arbitrator could be appointed disregarding Section 11(9). 

It was only in MSA Nederland B.V. v. Larsen and Toubro Ltd. (2005) 13 SCC 719 that the interpretation of Section 11(9) took a new turn. In that case, the Supreme Court misread Grid Corporation as holding that it was not mandatory for the Supreme Court to follow Section 11(9) when Grid Corporation did not state so at all. Consequently, MSA Nederland insofar as it permitted to deviate from Section 11(9) for no reason is not good law. In the present case, the Supreme Court tried to distinguish Malaysian Airlines and MSA Nederland by stating that these cases "can not be read to mean that in all circumstances, it is not possible to appoint an arbitrator of a nationality other than the parties involved in the litigation." (Para 72) The court also recognised that "the trend of the third arbitrator/ presiding officer of a neutral nationality being appointed is now more or less universally accepted under the Arbitration Acts and Arbitration Rules in different jurisdictions." (Para 73) The court's views can be restoring the original position that neutrality is a relevant consideration in such a petition. 

It is to be noted that the correct position is that that the court should, by default, ensure appointment of a neutral national as arbitrator. This is so, considering the well-settled practice of appointment of a neutral national as the sole arbitrator or the third arbitrator in a three member tribunal However, in case the parties express their consent to appoint a non-neutral national, Section 11(9) should not operate against the autonomy of the parties. It is possible that parties might have agreed to a non-neutral arbitrator in view of the additional travel, venue and related costs incurred in appointing a foreign arbitrator, especially if the seat is India.

Power of a party nominated arbitrator to tender legal advice: 

The judgement also raises this interesting question as to whether a party nominated arbitrator can tender legal advice to such party in relation to the appropriate time to approach the court under Section 11 of the Act. In this case, when Justice Bharucha and Justice VN Khare could not agree on the third arbitrator for a long time, Justice Bharucha wrote to Reliance: "In these circumstances, you must consider whether the court should be approached for the appointment of a third arbitrator." With utmost respect, it was not necessary for the party appointed arbitrator to advise Reliance to consider whether it should approach the court for the appointment of the third arbitrator. It would have been enough for the arbitrator to simply state that the arbitrators could not agree on the third arbitrator. Although this does not indicate any bias, such an advice is beyond the function of the arbitrator and could have been avoided. It may be noted that this is not an isolated incident. In fact, in Grid Corporation of Orissa Ltd. v. AES Corporation (2002) 7 SCC 736, the Supreme Court notes:

"13. On 1.2.2002, the petitions (sic petitioners) appointed Justice S.C. Mohapatra,retired Judge of High Court of Orissa and Allahabad and former Chairmanof Orissa Administrative Tribunal as their Arbitrator in place of Mr. Verma,in view of his having withdrawn from arbitration. On 1.2.2002, JusticeS.C. Mohapatra addressed a communication to Mr. Donovan requestinghim to agree for the appointment of a former Judge of Supreme Court ofIndia (named in the letter) to be the third Arbitration. It is also stated that ifMr. Donovan was not agreeable then the petitioners would move the ChiefJustice of India under Section 11 of the Act for appointment of a thirdarbitrator. Copy of the communication was endorsed to Mr. Williams also." (emphasis added)

Here, the party appointed arbitrator threatened the other party appointed arbitrator that if the latter did not agree for an Indian arbitrator, the party which appointed the former arbitrator would petition the Supreme Court under Section 11. With immense respect, it is submitted that it was not right on the part of the said arbitrator to act as a counsel of the party which appointed such arbitrator. 

The decision of the Supreme Court can be accessed from here and here (pdf).

Thursday, December 20, 2012

Relationship between Operator and the Non-Operators in Petroleum Operations

In the last post, we had discussed the decision of the Delhi High Court in HLS Asia Ltd. V. Geopetrol International Inc. & Ors where it was held that although the Non-Operators may not have been party to the contract between the Operator and the Contractor which contains the arbitration clause, they would be necessary parties to the arbitral proceedings in light of the interrelationship between the Operator and the Non-Operators as the members of the Consortium in terms of the Production Sharing Contract (JOA) and the Joint Operating Agreement (JOA). This series of short posts discusses this interrelationship between the Operator and Non-Operators. In this post, the concept of Operatorship in general is analysed.
Concept of Joint Operations:
Petroleum exploration is a highly risky business. Typically, such a company will encounter the following risks:
  • Geological risks- risk of not finding any petroleum in commercially viable quantities
  • Financial risks- risk that exploitation of the commercially viable quantities of petroleum is far complicated and therefore costlier than initially estimated or change in the economic laws of the host nation drastically increasing the costs to be expended
  • Political risks- instability in the region such as civil war, riots, etc thereby resulting in loss of investments.
The business is characterised by high input costs, and when there is commercial discovery, huge profits. Considering the high risks and costs, it is common for two or more parties to share the risks inherent in the business. The term “Contractor” in the Indian context is employed to collectively denote the companies engaged in petroleum exploration. Although the risk is shared, the same is always not equal. Each Party comprising the Contractor generally commits itself only to a certain amount of risk in the exploration project. Consequently, it is entitled to the reward only to the extent of the percentage of the risk shared. Such percentage is known as Participating Interest. Thus, all the rights and all obligations of whatsoever nature including privileges, entitlements, duties, penalties, etc are shared between the consortium members in accordance with their Participating Interest percentage. The percentage of Participating Interest held is recorded in the PSC as well as in the JOA.
Relation between Operator and Non-Operators:
In order to conduct the petroleum operations smoothly and in a focussed manner, a member of the consortium, usually the party having the highest participating interest and resources, is nominated as the Operator. The Operator is responsible for performing virtually all the operations, obtain approvals, comply with laws, employ contractors, and do all activities necessary to perform the petroleum operations. In performing these obligations, the Operator acts not only on behalf of itself but also on behalf of the Non-Operators. The Operator is also authorised to enter into contracts on behalf of the consortium. Thus, the Operator, apart from acting on its behalf, also acts for, or, represents the Non-Operators in dealings with third persons.
Although the Operator is authorized to act as the agent of the Non-Operators, the contours of such authority are delineated by the JOA. In addition, a body called the Operating Committee consisting of representatives of all members of the consortium (typically) is constituted to supervise the functioning of the Operator. Certain important actions in conducting petroleum operations require express authorization from the Operating Committee. Three possibilities exist as regards approval of Operating Committee for awarding contracts:
  1. the JOA authorizes the Operator to award contracts without the approval of the Operating Committee,
  2. the JOA authorizes the Operator to award only contracts below a specific value without the approval of the Operating Committee, and
  3. the JOA requires all contracts to be approved by the Operating Committee. In such cases, the Operator is bound to follow relevant procedure, as applicable. If no consent is taken when the JOA makes it mandatory, the Non-Operators would be entitled to refuse to share the costs and risks for such contracts.
Since the Operator is authorized to enter into contracts to conduct petroleum operations, it is expected that claims or legal proceedings may be initiated against the Operator. Generally, the Operator is authorized to represent the members of the consortium in defending legal proceedings. In doing so, the Operator is mandated to obtain the approval and direction of the Operating Committee in proceedings with such legal proceedings. Costs expended for defending the said proceedings are shared by the members proportionate to their Participating Interest. However, the Non-Operators are not prohibited from appointing their own counsel, in which case, the resultant costs are borne by the Non-Operators. In case a claim is initiated against a Non-Operator by a third party in respect of the petroleum operations, the Non-Operator is entitled to defend the same but in consonance with the directions of the Operating Committee and the costs expended for the same would be shared as per the Participating Interest.
In all, while performing the role of Operator, whether in conducting petroleum operations or in dealing with the government or third parties for the purposes of petroleum operations, the Operator acts as agent for the Non-Operators. Consequently, the general principles of the law of agency are applicable. It may be noted that the JOA grants restricted authority to the Operator to act as agent. Such authority is also circumscribed by the directions of the Operating Committee as provided by the JOA. Thus, subject to the JOA, the Operator is entitled to all the rights of an agent available under law. Such rights include the right to be indemnified by the Non-Operators against consequences of acts which are lawful and acts done in good faith, right to retain expenses incurred and his remuneration from moneys collected by him on behalf of principal, etc. At the same time, the Operator is, subject to the JOA, obligated to perform the duties of an agent as per law.
The above discussion generalises the concept of Operatorship prevailing in the petroleum industry. In the next post, the concept of Operatorship as found in some of the standard formats of agreements used in the petroleum industry would be discussed.

Tuesday, July 19, 2011

Bombay High Court Decides the Natural Gas Allocation Dispute

We have been following the Natural Gas allocation dispute over the past two months. For the uninitiated, check out the previous posts from here, here, here, here, here and here. The dispute was pending before the Bombay High Court for some time. On 8 July 2011, the Bombay High Court has decided the dispute in favour of Union of India. In this post, we summarize the judgement of the judge bench of the High Court consisting of Mohit S Shah, CJ. & Girish Godbole, J.Before that, we briefly note the events that led to the case.

12.07.10        The Ministry of Petroleum and Natural Gas (MOPNG) wrote to Reliance asking it to make pro-rata cuts in the supply of natural gas to all its customers when the production from Reliance Industries Limited’s (RIL) D 6 field was not sufficient to cater to all its customers.

30.03.11        Letter from MOPNG to RIL & Niko (NECO) Ltd. (Niko) noted that there was a marked decrease in the production of natural gas from the D 6 field which has led to substantial cuts in the natural gas quantities supplied to its customers. MOPNG stated that reduction in supply of natural gas (a) had subsidy implications on the fertilizer industry and (b) affected power plants, the domestic gas (Liquid Petroleum Gas & City Gas Distribution) sectors which in turn affected large number of people throughout India. The letter, therefore, directed RIL to supply gas to meet the demand from these sectors. The communication provided further that in case the existing production was insufficient to meet the demand of the sectors, cuts were to be imposed in the particular order among these sectors.

21.04.11          Letter from MOPNG to RIL &Niko (NECO) Ltd. (Niko) reiterating that the direction of the government vide letter dated 30.03.2011 needs to be complied with. The letter noted that in the RNRL v. RIL judgement the Supreme Court had noted that Government owned natural gas till it reached the consumer.

Against this direction, Welspun Maxsteel Ltd (Welspun) and Ispat Industries Ltd (Ispat) filed a writ petition in the Bombay High Court and claimed the following relief:

a) a writ, order or direction in the nature of certiorari calling for the records pertaining to the directives issued by [Union of India-UoI] to RIL and Nikovide letters dated March 30, 2011 and April 21, 2011 [hereinafter referred to as the “Impugned Directives”] and after examining the legality and validity thereof, be pleased to quash the impugned Directives;

b) issue a writ, order or direction in the nature of mandamus directing UoI to conduct an exhaustive investigation into the affairs of RIL and Niko in respect of the extraction of natural gas from the KG D6 fields and to issue appropriate directions to ensure that the maximum production levels from the KG D6 fields are attained;

The interim directions of the Bombay High Court have been covered adequately in the previous posts (here and here). The decision of the Bombay High Court is summarized below.
  • The Petitioners (Welspun Maxsteel & Ispat Industries) contend that once the MOPNG made firm allocation of natural gas and asked the Petitioners to enter into Gas Sale and Purchase Agreements (GSPA) with the Contractor (RIL & Niko), curtailment in the supply of natural gas cannot be done. As has been held by the Supreme Court in the case of RNRL v. RIL, ownership of natural gas is vested with the Union of India (UoI), which holds the scarce natural resources in public trust. In the same case, the Gas Utilization Policy of the UoI has been held to be in conformity with the Constitution. Significantly, the decision holds that the UoI has the power "regulate and distribute the manner of sale of natural gas through allotments and allocation which would subserve the best interests of the country." The judgement also states unequivocally that the Production Sharing Contract would "override any other contractual obligation between the contractor and any other party”, including the Gas Sale and Purchase Agreement (GSPA).
  • The Petitioners argue that the EGOM's (Empowered Group of Ministers) Policy has been entirely overhauled by the MOPNG. A perusal of the decisions of the EGOM shows that the EGOM had accorded high priority to certain sectors such as fertilizer etc (Core Sectors). Also, as per the decisions of the EGOM, firm allocation to steel plants such as those of the Petitioners would be only after demand from the core sectors were met. Therefore, there is no basis in the Petitioners' contention. Similarly, the contentions of the Petitioners that the MOPNG does not have any power to curtail the supply if the daily production is above 40 mmscmd must fail. In fact, all EGOM decisions empower the MOPNG "to take decisions regarding the supply of natural gas to sectors/individual customers consequent to gas being available on account of short offtake, delay and any other unforeseen circumstances." (Emphasis in the original) The EGOM has laid down the broader policy regarding the determination of core and non-core sectors, the overall principles regarding supply allocation and distribution and has empowered the concerned Ministry, the MOPNG, to implement its decisions in public interest.
  • The Petitioners rely on the doctrine of promissory estoppel. According to them, since the EGOM decided on the allocation to the steel industry and when firm allocations were made to the petitioners, the government cannot curtail the supply of natural gas in view of the doctrine of promissory estoppel. The Petitioners contention cannot be upheld. Natural gas is a scarce resource and the decision taken by the MOPNG was in public interest. It has been recognised in several decisions of the Supreme Court, including in Shrijee Sales vs Union of India, Kasinka Traders vs Union of India, M. P. Mathur Vs. DTC and State of West Bengal Vs. Niranjan Singha, that there can be no promissory estoppel against public interest
  • In proceedings pertaining to judicial review of administrative action, courts do not review the merits of the decision but merely review the decision making process. The Petitioners have, in effect, asked to court to sit on appeal over the decision of the MOPNG, which is not possible.
[On 18.05.2011, the MOPNG considered the submissions of the Petitioners and others in detail and passed a detailed order reiterating its position in the Impugned Directions. The High Court held that the decision was supported by "reasons which are cogent, germane, in consonance with the policy and law and cannot be termed as arbitrary."]
The court, while concluding, clarified that they were not deciding on the second prayer of the Petitioners (conduct an exhaustive investigation into the affairs of RIL and Niko in respect of the extraction of natural gas from the KG D6 fields) and asked the Petitioners to put forth their grievance before the UoI.

By the way, the court wrongly referred to natural gas as CNG (Compressed Natural Gas). What is explored is natural gas. Natural gas is found alongwith certain impurities. The same is sent through pipelines to a Gas Processing Plant, which basically removes the impurities and is sent further, usually through pipelines. Natural gas is compressed and used in pressurized tanks as fuel.

Thursday, June 23, 2011

Gas Dispute, Cairn's Revenge, the Production Sharing Contract: Updates

Lots of things happening in the petroleum arena. I call the petroleum sector an arena because its the most happening sector as far as disputes are concerned!

Gas Allocation Issue:
The Bombay High Court has reserved its judgement on the issue of non-allocation of gas from the Reliance D- 6 Field to the steel industry. We have been following this issue for some time (previous posts from this label). Moneycontrol.com has reported that the Ministry of Petroleum and Natural Gas has filed a reply to the petition of Maxsteel Welspun and others. Key aspects of the response, as per the report are the following:
  •  Gas allocation to the fertilizer sector should be prioritized due to the Kharif Season.
  • The power sector needs priority because of the extreme summer conditions.
  • This action by the Government would lead to savings in subsidy to the tune of Rs. 1251 crores to the government
Against this, it was contended that the Government has completely overhauled the extant policy on natural gas. Further, it was argued that if there was a reduction in gas production, there should be pro-rata cuts by the Government in respect of all sectors.

The steel companies counsel forwarding the point that if there is a reduction in the production of gas from the KG-D6 basin then the oil ministry should form this particular policy of pro-rata cuts for all sectors across the board in the range of 10-15%.

Cairn's Revenge?:
Cairn is now acting like a woman scorned. Readers must be aware of the Cairn-Vedanta deal and how the Government-ONGC combine is still holding both Cairn and Vedanta by their respective kudumis! Now, Cairn India has alleged that ONGC has overstated its gas reserves in the KG-DWN Block 98/2 Block. Cairn India is in fact a part of the ONGC-Cairn consortium that has been given the licence to explore the Block. This allegation makes the Cairn-Vedanta-MoPNG saga more interesting, especially when ONGC is coming up with an FPO. Meanwhile check out a few news reports on the issue- Times of India, Business Standard

PSC:
More trouble in the petroleum exploration business. The Comptroller and Auditor General's office has come up with a 193 page Draft Report on Hydrocarbon Production Sharing Contracts alleging that it has structural flaws, the major one being that the PSC encourages more capital expenditure by the Contractor thereby reducing the government's share of the profits from the petroleum produced. Check out this news report. This blawgger couldn't get hold of the report but if anyone has a copy of it, please mail it to lawbadri@gmail.com so that we could do a series of posts on the report.

Wednesday, May 11, 2011

Gas Allocation & Utilization in India: Further Developments

In our last post, we had dealt with the case pertaining to allocation of natural gas. In the case filed by Welspun Maxsteel and Ispat, the Bombay High Court had directed the Government to hear the concerns of the petitioners. The counsel for the Government stated in the court that the Government would hear the petitioners as well as others who were affected by the directions given to Reliance to supply gas only to priority sectors. Pursuant thereto, the Government has called for a meeting to be conducted today (May 11, 2011) chaired by the Joint Secretary (Marketing), Ministry of Petroleum & Natural Gas for hearing the affected parties.

Tuesday, May 10, 2011

Natural Gas Allocation and Utilisation in India: Matter Goes to Court

Reliance D 6*
Several newspapers in the last few days have reported petitions against the Ministry of Petroleum & Natural Gas, Government of India (MOPNG), for prioritizing the allocation of natural gas from the Reliance KG-D6 to specific industries. Essar Steel has, reportedly, filed a petition before the Delhi High Court against the order of the MOPNG dated April 21, 2011 (Direction) allocating gas from Reliance’s KG D6 Field to “priority” sectors such as fertilizers, power etc, and only after the demand in the sectors are met, to sectors such as steel, petrochemicals and refineries.The per day demand of priority sector seems to be around 47.6  million metric standard cubic meters per day (mmscmd). The Direction seems to empower Reliance to cut off supplies to non-priority sectors if the natural gas demand of the priority sectors has not been met. Consequently, Reliance Industries Limited (RIL) has reportedly cut off the natural gas supply to such non-priority sectors from this Monday (10.05.2011).

About 3.2 mmscmd gas was supplied from D6 to Essar Steel. However, of late, D6 field has not been producing enough natural gas, leading to strict directions from the Exploration & Production regulator-Directorate General of Hydrocarbons to RIL. This Direction is a possible consequence of the low production. Essar Steel challenged the Direction to RIL. Essar Steel had also asked for an interim stay on the direction of the MOPNG. However, the Delhi High Court refused to grant stay without hearing the Government. When the court asked for the contentions of the Government with the Additional Solicitor General, Mr A.S. Chandiok (ASG), the ASG asked for more time to review the decision of the Bombay High Court on a similar matter that arose out of petitions filed by Welspun Maxsteel and a few others.

Proceedings before the Bombay High Court:
The Direction was also the subject matter of a petition filed in the Bombay High Court by Welspun Maxsteel. Relevant portions of the impugned Direction dated April 21, 2011 reads as follows: 
“2. Under the Government's Gas Utilization Policy, allocations for KG D6 fields had initially been made for core sectors and subsequently, taking into account expectation of higher production, allocations had been made for non-core sectors. As the gas production from KG D6 fields has decreased to around 50 mmscmd, it is only natural that the said production be supplied firstly to core sectors and Ministry's direction vide letter of even number dated 30.03.2011 has been issued in this context. The said direction has been issued in pursuance of Government's Gas Utilization Policy under the provisions of the PSC. Hence, the said direction needs to be complied with.
3. The Hon'ble Supreme Court in its order dated 7.5.2010 in the RIL & RNRL case has held that the Government owns the gas till it reaches its ultimate consumer. Further, it has been held that the PSC shall override any other contractual obligation between the Contractor and any other party.”
It may be noted that he MOPNG has been deciding on the allocation of natural gas to different sectors for a long time. As regards natural gas from the D6 Field, Government had, though an EGoM (Empowered Group of Ministers), framed a policy, known as Gas Utilisation Policy (June 2008), for the allocation of gas to various sectors. The said policy also contained certain general directions for the allocation of natural gas in respect of all NELP (New Exploration Licence Policy) Production Sharing Contracts. Following are the features of the general guidelines:
  • The marketing priorities for the sale of gas from NELP Blocks would be determined by the Government and the sale would be on the basis of pricing formula approved by it.
  • Gas allocation to a particular sector would not mean reservation or quota to that particular sector. In case consumers of a particular priority sector are not in a position to take gas when available, the gas not taken would be first offered to other entities in that priority sector and if they are not in a position to take the gas, the gas not taken would go to the sector which is next in priority.
  • The priority for gas supply would be applicable only to customers who are connected to the existing pipelines network. In the absence of a network, a small or marginal field could sell the gas to customers connected to or can be connected to (within a short period of three- six months) it.
  • This prioritization would not affect the process of price discovery as all customers would participate in the price discovery process (as per the extant policy of the EGoM) and would be eligible for utilizing natural gas subject to priority.
  • This guidelines would be reviewed after five years 
Apart from these general guidelines, the policy prioritized sectors for the utilization of the D6 gas. The priority sectors as per the policy are:
  • Gas based urea plants
  • Gas based LPG plants
  • Liquid Fuel plants and power plants lying idle or underutilized
  • City Gas distribution
  • Gas based power plants
There are two sources of such power of the Government. One, the Production  Sharing Contract itself gives the Government the right to frame policies pertaining to marketing of natural gas. The relevant provisions in the latest (NELP IX) PSC are as follows: 
"21.1 Until such time as the total availability of Natural Gas from all Petroleum production activities in India meets the total national demand as determined by the Government, each Company comprising the Contractor, shall sell in the domestic market in India all of the Company’s entitlement to Natural Gas from the Contract Area.
21.3 For the purpose of domestic sale obligation, the Contractor shall have freedom to market the Natural Gas and sell its entitlement as per Government Policy for utilization of gas among different sectors. 
21.3.1 For purposes of Article 21, the Government may from time to time frame policy for utilization of gas among different sectors, both for Associated Natural Gas (ANG) as well as Non-Associated Natural Gas (NANG) which would cover issues relating to gas supplies to different consumer sectors."
The second source comes from the Constitution itself. Article 73 read with Entry 53, List I of Schedule VII. Entry 53 reads:
"Regulation and development of oilfields and mineral oil resources; petroleum and petroleum products; other liquids and substances declared by Parliament by law to be dangerously inflammable."
Now, in the Welspun Maxsteel case, it was argued that if no gas was supplied to the petitioners, their manufacturing process would come to a standstill and this would have a cascading effect on the economy. A two judge Bench consisting of Ranjana Desai & Ranjit More, JJ. were of the opinion that the Union of India has to hold a meeting with the petitioners to sort out their grievance. The Bench ordered the matter to be heard on May, 9, 2011. The order can be accessed from here. On May 9, the Vacation Bench consisting of Mridula Bhatkar & RG Ketkar, JJ heard the matter.In the said hearing, the counsel for Union of India stated that a meeting would be conducted on May 11 between the petitioners, representatives of other non-priority sectors affected by the decision of the Government, and the MOPNG and a decision on the matter would be communicated to the petitioners by May 19, 2011. The court adjourned the matter to May 23, 2011. The order can be downloaded from here.

It would be interesting to see what the MoPNG would do. We will keep our readers updated.

* Image from here.