Richard Feynman made this statement criticising relying on formulas to study physics and instead focus on the underlying reality. He was of the view that one could not get anywhere merely based on the formulas. This criticism holds good for construction law too.
Indian courts have criticised claims by construction contractors based on formulae such as Hudson, Emden, etc, and have required evidence of losses. So many arbitral awards have been set aside on this ground. Some awards could escape courts’ attention.
The Construction Contract
- Work: Construction of seventy-six flats for officers at Sector-62, Noida
- Letter of Award: 22.12.2012
- Agreement: 16.01.2013
- Contract Value: 19.81 crores
- Scheduled Contract Completion Date: 15.01.2015 (25 months)
- Extensions: 3
- Actual completion date: 23.08.2016
Arbitration and Challenge
Contractor, KR Anand, invoked arbitration and made several claims. There were a total of 17 claims. Arbitrator awarded Rs. 1.43 crores to the contractor. SBI challenged the award in the Delhi High Court on 3 claims.
Decision of the Delhi High Court on Award on Claim 1
Claim 1 was for loss of overhead expenditure of Rs. 65.81 lakhs. Rs. 20.27 lakhs was awarded. There were two main problems with this part of the award. The arbitrator attributed 205 days of delay to the contractor and 175 days to SBI but chose to decide the claim in favour of the contractor. Another problem was that there was no evidence of losses. The contractor chose do defend the award on the basis of the Emden formula. We are concerned in this post about the second limb of the arbitrator's reasoning: reliance on Emden formula.
Proof of actual loss is essential. The Delhi High Court reiterated the settled law that proof of losses is required through evidence and formulae cannot substitute evidence. The court cited the Unibros decision and held: “The Supreme Court in Unibros v. All India Radio (supra) held that reliance on a formula is not a substitute for establishing the loss actually suffered… 13. In the case in hand the damages awarded relying upon the Emden Formula in the absence of evidence to prove the actual loss suffered is contrary to the settled position of law”.
The court considered the award on this claim to have been given in disregard of the Contract Act, which required proof of losses (Para 11). The court gave another dimension to the matter: An award that relies on formula as a substitute for proof of actual losses suffers from lack of reasoning and violates Section 31(3) of the Arbitration and Conciliation Act, 1996:
“However, even on a fair reading of the award as a whole no reason emanates for the arbitrator accepting the calculation based on the Emden formula without there being evidence to prove the loss suffered or that it was difficult or impossible to prove the actual loss suffered. The award of claim no.1 falls within the teeth of Section 31(3) of the Act.”
Credibility of Arbitration
There are so many judgments that dealt with the proposition that the Delhi High Court was relying on. See, for instance,
here and
here. Despite this, the arbitrator chose to award this claim in favour of the Contractor. Such arbitral awards justify DOE’s OM of 03.06.2024.