"I realise that some of my criticisms may be mistaken; but to refuse to criticize judgements for fear of being mistaken is to abandon criticism altogether... If any of my criticisms are found to be correct, the cause is served; and if any are found to be incorrect the very process of finding out my mistakes must lead to the discovery of the right reasons, or better reasons than I have been able to give, and the cause is served just as well."

-Mr. HM Seervai, Preface to the 1st ed., Constitutional Law of India.

Friday, September 18, 2026

Formulaic Claims, Arbitral Awards and the Credibility of Arbitration


Richard Feynman made this statement criticising relying on formulas to study physics and instead focus on the underlying reality. He was of the view that one could not get anywhere merely based on the formulas. This criticism holds good for construction law too.

Indian courts have criticised claims by construction contractors based on formulae such as Hudson, Emden, etc, and have required evidence of losses. So many arbitral awards have been set aside on this ground. Some awards could escape courts’ attention.

Arbitral awards awarding claims based on formulae when there is no or inadequate evidence justify the Department of Expenditure’s Office Memorandum 03.06.2024 that discourages arbitration. One such case is SBI v. KR Anand, 2026:DHC:7793.

The Construction Contract
  • Work: Construction of seventy-six flats for officers at Sector-62, Noida
  • Letter of Award: 22.12.2012
  • Agreement: 16.01.2013
  • Contract Value: 19.81 crores
  • Scheduled Contract Completion Date: 15.01.2015 (25 months)
  • Extensions: 3
  • Actual completion date: 23.08.2016
Arbitration and Challenge

Contractor, KR Anand, invoked arbitration and made several claims. There were a total of 17 claims. Arbitrator awarded Rs. 1.43 crores to the contractor. SBI challenged the award in the Delhi High Court on 3 claims.

Decision of the Delhi High Court on Award on Claim 1

Claim 1 was for loss of overhead expenditure of Rs. 65.81 lakhs. Rs. 20.27 lakhs was awarded. There were two main problems with this part of the award. The arbitrator attributed 205 days of delay to the contractor and 175 days to SBI but chose to decide the claim in favour of the contractor. Another problem was that there was no evidence of losses. The contractor chose do defend the award on the basis of the Emden formula. We are concerned in this post about the second limb of the arbitrator's reasoning: reliance on Emden formula.

Proof of actual loss is essential. The Delhi High Court reiterated the settled law that proof of losses is required through evidence and formulae cannot substitute evidence. The court cited the Unibros decision and held: “The Supreme Court in Unibros v. All India Radio (supra) held that reliance on a formula is not a substitute for establishing the loss actually suffered… 13. In the case in hand the damages awarded relying upon the Emden Formula in the absence of evidence to prove the actual loss suffered is contrary to the settled position of law”.

The court considered the award on this claim to have been given in disregard of the Contract Act, which required proof of losses (Para 11). The court gave another dimension to the matter: An award that relies on formula as a substitute for proof of actual losses suffers from lack of reasoning and violates Section 31(3) of the Arbitration and Conciliation Act, 1996:

“However, even on a fair reading of the award as a whole no reason emanates for the arbitrator accepting the calculation based on the Emden formula without there being evidence to prove the loss suffered or that it was difficult or impossible to prove the actual loss suffered. The award of claim no.1 falls within the teeth of Section 31(3) of the Act.”

Credibility of Arbitration

There are so many judgments that dealt with the proposition that the Delhi High Court was relying on. See, for instance, here and here. Despite this, the arbitrator chose to award this claim in favour of the Contractor. Such arbitral awards justify DOE’s OM of 03.06.2024.

Thursday, September 17, 2026

Costs Not Recoverable under the Sri Lankan Model Petroleum Resources Agreement

 Sri Lanka's Model Petroleum Resources Agreement (2026) (SLMPRA) is one of the recent Production Sharing Contracts (PSC) published and available. Link to the SLMPRA is provided at the end of this post. For a PSC, the length of the SLMPRA is only 95 pages. Cost recovery is one of the important provisions of a PSC. Costs allowed to be recovered and costs not allowed to be recovered form some of the crucial provisions of a PSC. This post discusses the cost items which are not recoverable.

Article 21 of the SLMPRA deals with Recovery of Cost Petroleum. Article 1 defines "Agreement Costs" as "Exploration Costs, Development Costs and Production Costs as provided for in the PRA and which are deemed to be recoverable costs in terms of Article 21 of the PRA;". Article 21.2 classifies these costs into "Production Costs", "Exploration Costs" and "Development Costs" incurred by the Contractor.

Article 21.12 pertains to costs not recoverable. It contains a whopping list of 31 items! If these costs can be classified into distinct buckets, such a classification would be as follows:

Category

Description

Clause / Item Numbers

Before SLMPRA or outside Area/ Outside Sri Lanka

Costs before Effective Date, costs related to administrative overhead outside of Sri Lanka for specific items; Income/ other tax incurred outside Sri Lanka; Costs outside measurement point

1, 4, 9, 10, 19

Specific Payments/ Costs/ obligations under MPRA

Expenditure incurred in obtaining, furnishing and maintaining the guarantees, expenses of the members of the Advisory Committees and other Committee, Environment studies protection, Abandonment fund, Training costs. Production bonus, Signature bonus, royalty,

17, 25 to 31

Excess costs/ gold plating/ negligence/ misconduct/

costs of goods and services in excess of the international market price for goods or services; charges for goods and services not in accordance with the relevant agreement with sub-contractor or supplier; Charges for goods in excess of the amount allowed by Article 21.12; Costs not reasonably required for petroleum operations; costs of materials and services in excess of the values established under the principles in Article 21.12; costs and expenditure as result of wilful misconduct or negligence of Contractor;

5, 6, 7, 8, 20, 24

Unsupported/ Unapproved Costs

costs for which original records do not exist or are not correct in any material respect; any costs not included in approved work program and budget, unless resulting from an emergency; Emergency expenditure incurred but not reported within time

3, 14, 16,

Fines/ penalties

fines and penalties imposed by any Authority

12

Non-fulfilment of contractual obligations with third parties

amounts paid with respect to non-fulfilment of a contractual obligation to a third party; Indemnities spent on Non-fulfilment of contractual obligations with third parties

17, 22

Unrelated to petroleum operations

Expenditures for securing funds for petroleum operations; donations, contributions, or public expenditure; costs involved in creation and management of any partnership/ joint venture arrangement, or costs of acquisition of an interest under the Agreement

2, 13,21

Dispute resolution

Costs of expert determination of arbitration; attorney’s fee and other costs related thereto.

11, 18

Others

costs incurred which are covered by insurance for Included Risks, are a result of failure to insure where insurance is required pursuant to the Contract, etc.

23

The items not cost recoverable have been classified into nine distinct buckets. This PSC has one of the longest list of items that are not cost recoverable. Like in any other PSC, there are bound to be disputes on individual items in this long list. 

It would be interesting to see if the recent Model PSCs disclose such a trend, given their experience and experience of other countries in dealing with cost recovery related issues. 

Sri Lanka MPRA (2026) can be downloaded from here.